Save this project to account
Connected planning records

Planning case 2360333

Westmeath County Council · 2360333 · Clonmellon, Westmeath

Latest linked evidence

Notified commencement · 2026-09-15

Construction of 11 no. units having house number 12,13,14, 17,18, 21,22,23,24,25,26 out of the total 26 units. Other units were constructed in phase 1 and 2

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

Decision recorded; appeal window open and no exact commencement link. Scale reflects the permitted decision record.

4 official documents inspected · Checked 2026-09-19 · Official file index

Landscaping

Decision record · Westmeath County Council 2360333 official inventory date date not stated: application scheme as submitted or assessed at that date, evidenced by Drainage Network Drawings, Planners Report - FI, Resource & Waste Management Plan; any later dated revision is a separate state.

What the evidence says
landscaping

Machine-extracted from the official document; automated reviewed for publication.

Why it may matter — interpretation
Exact official wording retained for any downstream trade or planning lens to read without re-extracting the documents.

What is not established
Machine-extracted and automated reviewed; later revisions, conditions, approvals and construction outcomes are not established.

Inspect the evidence

Planners Report - FI · p.1
Page 1 · Issued Not stated · Westmeath County Council 2360333 - Planners Report - FI (planner_report); date not stated in the official inventory; retained revision sha256:f052c217ab90 · Checked 2026-09-19

landscaping

Managers Order MG8108 EOT · p.1
Page 1 · Issued Not stated · Westmeath County Council 2360333 - Managers Order MG8108 EOT (decision_record); date not stated in the official inventory; retained revision sha256:54d9ae5857c8 · Checked 2026-09-19

landscaping
Remaining document questions
  • Inspect any later revision the authority replaces at the same URL.
  • Link the commencement and completion events when they arrive.

4 retained official PDF revision(s) from the exact Westmeath County Council 2360333 file list. Machine extraction reads bounded passages; drawings are not interpreted.

Source history

Timeline

  1. Planning application received

    2360333

  2. Planning decision

    2360333

    Conditional permission

  3. Grant date recorded

    2360333

  4. Notified commencement

    Commencement notice

    1st phase of the development will consist of construction of total 7 no. units - 3 units in Block 1(H.N.1,2,3), 2 units in Block D (H.N 23,24) and 2 units in Block E (25,26) out of the total 26 units. Other units to be constructed in next phase.

    7 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of 4 no. units having house number -27,28,29,30 out of the total 26 units.Other units to be constructed in next phase

    4 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Development will consist of construction of 4 no. of apartments in this phase out of total 26 units which is to be constructed in different phases.

    4 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Construction of 11 no. units having house number 12,13,14, 17,18, 21,22,23,24,25,26 out of the total 26 units. Other units were constructed in phase 1 and 2

    11 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.