Save to pipeline
Connected planning records

Planning case SD19A0263

South Dublin County Council · SD19A0263 · Rathcoole, Dublin

Latest linked evidence

Notified commencement · 2020-08-17

New ESB Substation and Switch room at Site G Aerodrome Business Park, Road & Jordanstown Way, College Land, Rathcoole, Co. Dublin.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    SD19A0263

    Official source

  2. Planning decision

    SD19A0263

    Permission granted

    Official source

  3. Grant date recorded

    SD19A0263

    Official source

  4. Notified commencement

    Commencement notice

    Warehouse with ancillary three storey office and staff facilities and associated development at Aerodrome Business Park, Lands at Site G, Jordanstown Road & Jordanstown Way, College Land, Rathcoole, Co. Dublin. The warehouse will have a parapet height of 17m with a gross floor area of 11,012sq.m including a warehouse area (10,079sq.m), ancillary office areas (877sq.m) and staff facilities (56sq.m); provision of a new vehicular access/egress onto the Jordanstown Road, and the relocation of the entrance/exit on Jordanstown Way slightly to the west for HGV access; internal roadways; pedestrian access; 108 ancillary car parking spaces; bicycle parking; HGV yard including 13 HGV parking stands and 14 loading docks; hard and soft landscaping including green walls; lighting; photo-voltaic panels; plant; and associated development works above and below ground.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    New ESB Substation and Switch room at Site G Aerodrome Business Park, Road & Jordanstown Way, College Land, Rathcoole, Co. Dublin.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.