Planning case 171213

Galway County Council · 171213 · Parkmore, Galway

Latest linked evidence

Notified commencement · 2018-12-17

CN0047055GC · The construction and completion of Advance Technology Building, including reinforced Concrete (RC) foundations and ground floor slab, blockwork and RC rising walls, steelwork frame, composite metal cladding and curtain wall glazing, RC and blockwork walls and partitions, Composite floors and stairs, glazing and doors, M+E installations, lifts and associated siteworks. The unit will be completed to Category A level in the open production areas and in the office areas. The site is located at IDA Parkmore Business & Technology Park, Co Galway and the building will have an approximate gross floor area of 3,150 m2.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    171213

  2. Planning decision

    171213

    Conditional permission

  3. Grant date recorded

    171213

  4. Notified commencement

    CN0047055GC

    The construction and completion of Advance Technology Building, including reinforced Concrete (RC) foundations and ground floor slab, blockwork and RC rising walls, steelwork frame, composite metal cladding and curtain wall glazing, RC and blockwork walls and partitions, Composite floors and stairs, glazing and doors, M+E installations, lifts and associated siteworks. The unit will be completed to Category A level in the open production areas and in the office areas. The site is located at IDA Parkmore Business & Technology Park, Co Galway and the building will have an approximate gross floor area of 3,150 m2.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.