Planning case 2050920

Donegal County Council · 2050920 · Donegal, Donegal

Latest linked evidence

Notified commencement · 2023-08-21

2 storey extension to existing secondary school to provide new GP Room, kitchen and toilet on the ground floor and new classrooms and library and toilets on the first floor, with stair and lift. Steel frame, precast concrete floor units, masonry cavity external walls, with steel purlins and timber joisted roof structure.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2050920

  2. Planning decision

    2050920

    Conditional permission

  3. Grant date recorded

    2050920

  4. Notified commencement

    Commencement notice

    2 storey extension to existing secondary school to provide new GP Room, kitchen and toilet on the ground floor and new classrooms and library and toilets on the first floor, with stair and lift. Steel frame, precast concrete floor units, masonry cavity external walls, with steel purlins and timber joisted roof structure.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.