Planning case 187156

Cork County Council · 187156 · Innishannon, Cork

Latest linked evidence

Notified commencement · 2019-05-17

A new warehouse facility and associated works located at the existing site at Brinny, including the following: The construction of a new warehouse building, the demolition of an existing gas bottle store, formation of a new site entrance on the L2235 and associated ancillary site services. The ancillary works include landscaping, underground and over-ground utilities, yards, associated siteworks and new external items of plant equipment. This application relates to a development which comprises or is for the purpose of an activity requiring an Industrial Emissions Directive Licence issued by the Environmental Protection Agency (EPA).

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    187156

    Official source

  2. Planning decision

    187156

    Conditional permission

    Official source

  3. Grant date recorded

    187156

    Official source

  4. Notified commencement

    Commencement notice

    A new warehouse facility and associated works located at the existing site at Brinny, including the following: The construction of a new warehouse building, the demolition of an existing gas bottle store, formation of a new site entrance on the L2235 and associated ancillary site services. The ancillary works include landscaping, underground and over-ground utilities, yards, associated siteworks and new external items of plant equipment. This application relates to a development which comprises or is for the purpose of an activity requiring an Industrial Emissions Directive Licence issued by the Environmental Protection Agency (EPA).

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.