Save this project to account
Connected planning records

Planning case 20156

Kildare County Council · 20156 · Ballitore, Kildare

Latest linked evidence

Notified commencement · 2024-04-23

CN0114488KE · Construct semi- detached dwelling and 2 No apartments at Sites 1-3 Strettel Avenue, Ballitore

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    20156

  2. Planning decision

    20156

    Conditional permission

  3. Grant date recorded

    20156

  4. Notified commencement

    CN0082222KE

    Construct 6 No semi-detached two-storey dwellings and a detached two storey dwelling on site 4 - 10 at Ballitore

    7 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    CN0087957KE

    Houses 11 to 14 Strettel Avenue, two storey semi-detached units

    4 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    CN0089311KE

    Construct three bungalows to sites 15,16 & 17 Strettel Avenue, Ballitore

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    CN0093555KE

    Construct two storey semi-detached houses on sites 18 to 33 Strettel Avenue, Ballitore.

    16 units stated for this notice or phase; not a project total.

    · Notice evidence

  8. Notified commencement

    CN0114488KE

    Construct semi- detached dwelling and 2 No apartments at Sites 1-3 Strettel Avenue, Ballitore

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.