Notified commencement · 2024-11-14

The development will consist of the full renovation and upgrading to the existing dining hall building (509 sqm) and the construction of a new single storey extension (231 sqm) to provide additional dining hall space for the school, located on a site of c. 0133 ha within the campus. The following works area proposed: installation of new gazing and upgrading of the fabric of the existing facades and roof of the Dining Hall; provision of new toilets (20sqm), additional dining area and sundry internal reconfigurations to the kitchen and servery; replacement of existing mechanical plant and a new uncovered plant enclosure at roof level (113 sqm); adjustment of existing adjacent parking layout; wayfinding signage and external lighting hard and soft landscaping in the immediate vicinity and all associated site excavation, utilities and site development works above and below ground (foul, surface water drainage and water supply). The works also include the demolition of a link corridor (47 sqm) between the existing dining hall building dormitory/ classroom building; the extension of the entrance lobby to include fire escape doors and the installation of double doors between the dining hall and dormitory/classroom building.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    367924

  2. Planning decision

    367924

    Permission granted

  3. Grant date recorded

    367924

  4. Notified commencement

    Commencement notice

    The development will consist of the full renovation and upgrading to the existing dining hall building (509 sqm) and the construction of a new single storey extension (231 sqm) to provide additional dining hall space for the school, located on a site of c. 0133 ha within the campus. The following works area proposed : installation of new gazing and upgrading of the fabric of the existing facades and roof of the Dining Hall; provision of new toilets (20sqm), additional dining area and sundry internal reconfigurations to the kitchen and servery; replacement of existing mechanical plant and a new uncovered plant enclosure at roof level (113 sqm); adjustment of existing adjacent parking layout; wayfinding signage and external lighting hard and soft landscaping in the immediate vicinity and all associated site excavation, utilities and site development works above and below ground (foul, surface water drainage and water supply). The works also include the demolition of a link corridor (47 sqm) between the existing dining hall building dormitory/ classroom building; the extension of the entrance lobby to include fire escape doors and the installation of double doors between the dining hall and dormitory/classroom building.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.