Connected planning records

Planning case SD20A0283EP

South Dublin County Council · SD20A0283EP

Latest linked evidence

Planning decision · 2026-07-21

SD20A0283EP · Decision recorded

Open official source

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

One-year extension granted by order dated 21 July 2026, expiring 23 June 2027. The May applicant report describes most of the parent permission as substantially complete; current site progress is not independently verified.

2 official documents inspected · Checked 2026-09-06 · Official file index

The permission now expires on 23 June 2027

Extension and source-reported progress; completion not independently verified · South Dublin SD20A/0283/EP; extension of the earlier SD20A/0283 permission

What the evidence says
The council decision dated 21 July 2026 grants a one-year extension of the existing permission, with an expiry of 23 June 2027. The notification was signed on 22 July. Its long development description repeats the older campus permission; this extension is not treated as approval for another pair of data-centre buildings or another equipment order.

Why it may matter — interpretation
Interpretation: distinguishes a consent-duration change from additional development scope.

What is not established
Subsequent amendments, completed remaining work and a completion certificate have not been verified.

Inspect the evidence

Microsoft campus: decision granting extension of duration · p.2
shall expire on 23rd June 2027 · Issued 2026-07-21 · Order 0818; notification signed 22 July; one-year extension to 23 June 2027 · Checked 2026-09-06

shall expire on 23rd June 2027

The application says the gas skid is the only remaining work

Extension and source-reported progress; completion not independently verified · Applicant-reported completion boundary for the existing campus permission

What the evidence says
The May extension submission reports the central administration building and DUB14/DUB15 data centres as substantially complete. It identifies the GNI gas skid as the only remaining work and shows that small area separately from the constructed development. This is the applicant’s reported progress at that date, not an independent inspection or evidence that all old generator and transformer quantities are new opportunities now.

Why it may matter — interpretation
Interpretation: prevents the repeated historic building and equipment description from being counted as an entirely new construction package.

What is not established
Current as-built progress, the detailed remaining skid specification and installed equipment are unverified.

Inspect the evidence

Microsoft campus: extension-of-duration application · p.11
The only remaining works are the GNI skid · Issued 2026-05-27 · Reported completion boundary and programme; existing permission and subsequent amendments remain distinct · Checked 2026-09-06

The only remaining works are the GNI skid

The stated 2026 target is separate from the extended expiry

Extension and source-reported progress; completion not independently verified · May reported programme for the remaining skid; later permission expiry is a separate milestone

What the evidence says
The May submission says skid construction had commenced and was due to finish during 2026. It seeks the additional year to allow for delays and anticipates completion by 2027 at the latest. These are source-reported programme expectations. The later council expiry of 23 June 2027 is a permission date, not evidence that commissioning is finished.

Why it may matter — interpretation
Interpretation: keeps planned completion, legal duration and actual completion distinct.

What is not established
A current construction programme, commissioned connection and verified completion date are not established.

Inspect the evidence

Microsoft campus: extension-of-duration application · p.13
construction of the GNI skid has commenced · Issued 2026-05-27 · Reported completion boundary and programme; existing permission and subsequent amendments remain distinct · Checked 2026-09-06

construction of the GNI skid has commenced
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 2 government-published PDFs were visually inspected. Nine literal public council document links were retained. Selected pages of two supporting PDFs were visually inspected. A third assessment PDF was text-screened only; this is not a comprehensive review of the older parent permission. Proposals do not establish procurement or installed work.

Source history

Timeline

  1. Planning application received

    SD20A0283EP

    Official source

  2. Planning decision

    SD20A0283EP

    Decision recorded

    Official source

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.