Council decision to grant dated 18 August 2026 with 31 conditions; selected notice is explicitly not the final grant. The energy and lighting reports were revised in June 2026. Finish agreement and final phase specifications remain open in the reviewed evidence.
The council decision specifies 136 homes
Council decision scale · Exact application 2661048 and its council decision; no national feed correction is made by this research
What the evidence says
Condition 1 explicitly specifies 136 residential units. The 18 August 2026 decision describes 21 two-bedroom,104 three-bedroom and 11 four-bedroom units, with 31 conditions. This source establishes the decision’s scale despite the retained feed’s structured value of 1.
Why it may matter — interpretation
Interpretation: replaces an unusable scale signal with an exact sourced quantity for this case.
What is not established
The notice is not a final grant, and does not establish commencement or completion.
Inspect the evidence
Raheen LRD: council decision and 31 conditions · p.2
a total of 136 residential units · Issued 2026-08-18 · Decision under section 34; not the final grant · Checked 2026-09-05
a total of 136 residential units
Stone restricted to natural limestone; finish colours still require agreement
Finishes require council agreement · Council condition 3; conditional finishes, not a final materials schedule
What the evidence says
Condition 3 requires finishes, materials and colours to be agreed in writing before commencement. Any stone finish is restricted to natural limestone; brick colour also needs written agreement.
Why it may matter — interpretation
Interpretation: identifies where specification remains subject to approval.
What is not established
A later written agreement, selected brick product, supplier and installed finish were not established.
Inspect the evidence
Raheen LRD: council decision and 31 conditions · p.2
natural limestone only · Issued 2026-08-18 · Decision under section 34; not the final grant · Checked 2026-09-05
natural limestone only
House heating uses air-to-water heat pumps; PV is described as enabled
Proposed in application · The report’s house section; final plot specification not established
What the evidence says
The revised energy report proposes an individual air-to-water heat pump for each house, supplying space heating and hot water. Its PV section describes enabling a future array rather than an already selected or installed panel schedule.
Why it may matter — interpretation
Interpretation: distinguishes the proposed heating technology from future-ready solar provision.
What is not established
No heat-pump brand, capacity, installed panels or procured package is established. The decision’s general PV wording does not resolve the report’s enabling-only detail.
Inspect the evidence
Raheen LRD: Sustainability and Energy Report · p.5
Air-to-Water Heat Pump · Issued 2026-06-05 · P1-P02; New Project Description; received 2026-06-24 · Checked 2026-09-05
Air-to-Water Heat Pump
Separate apartment sections describe exhaust-air heating and demand-controlled extraction
Proposed in application · Apartment sections of the exact application report; no allocation to every one of the 136 homes
What the evidence says
The same report has an apartment section proposing exhaust-air heat pumps and local 200-litre hot-water storage. Its ventilation section describes mechanical central extraction with demand control. These statements stay attached to the report’s apartment scope.
Why it may matter — interpretation
Interpretation: preserves distinct system approaches within the file.
What is not established
The reviewed decision does not allocate a number of homes to this apartment-system description. Final unit applicability, detailed coordination, brand and installation remain unestablished.
Inspect the evidence
Raheen LRD: Sustainability and Energy Report · p.7
Exhaust Air Heat Pumps · Issued 2026-06-05 · P1-P02; New Project Description; received 2026-06-24 · Checked 2026-09-05
Exhaust Air Heat Pumps
Raheen LRD: Sustainability and Energy Report · p.8
Demand Control Ventilation · Issued 2026-06-05 · P1-P02; New Project Description; received 2026-06-24 · Checked 2026-09-05
Demand Control Ventilation
A34-luminaire calculation using two AXIA3EVO variants
Proposed in application · June 2026 lighting design and calculation; not installed quantity
What the evidence says
The lighting report names Urbis Schreder AXIA3EVO. The attached calculation lists 2 luminaires of type 5266 and 32 of type 5267, giving 34 in the modelled layout. The report targets residential lighting ClassP4.
Why it may matter — interpretation
Interpretation: identifies a named lighting family and an exact design schedule.
What is not established
Final council agreement, substitutions, supplier order and installed light count remain unestablished. The source’s phrase 32 luminaire types is resolved only by the attached calculation’s 32 No. in Project.
Inspect the evidence
Raheen LRD: Public Lighting Report and Layout · p.6
Urbis Schreder Axia 3 EVO1 5266 · Issued 2026-06-19 · P1-P02; attached calculation layout dated 9 June 2026; received 2026-06-24 · Checked 2026-09-05
Urbis Schreder Axia 3 EVO1 5266
Raheen LRD: Public Lighting Report and Layout · p.12
No. in Project · Issued 2026-06-19 · P1-P02; attached calculation layout dated 9 June 2026; received 2026-06-24 · Checked 2026-09-05
No. in Project
Wall, roof and window targets remain subject to detailed design
Proposed in application · Proposed fabric targets for the application report; not measured performance
What the evidence says
The energy report targets ground-floor U-value up to 0.15 W/m²K, walls up to 0.18, roof 0.14–0.16 and windows or doors 1.2–1.4. It says final values will be confirmed during detailed design and updated in the energy assessment.
Why it may matter — interpretation
Interpretation: gives insulation and envelope teams the design intent and its limit.
What is not established
Final build-ups, certified products, as-built values and measured airtightness are not established.
Inspect the evidence
Raheen LRD: Sustainability and Energy Report · p.10
Final values will be confirmed during detailed design · Issued 2026-06-05 · P1-P02; New Project Description; received 2026-06-24 · Checked 2026-09-05
Final values will be confirmed during detailed design
Selected pages of 3 government-published PDFs were visually inspected. The exact council index lists 106 files. Only the cited pages of 3 selected government PDFs were inspected for these findings; other downloaded and indexed files are not counted as reviewed. Proposals do not establish procurement or installed work.