Infrastructure, Brennans Bakeries, Greenhills Industrial Estate, Greenhills... - Planning Application SD25A/0139W

South Dublin County Council · SD25A0139W · Dublin

Latest linked evidence

Notified commencement · 2026-06-16

CN0143598SD · Phase 2 - The development shall consist of demolition of the existing centrally located two storey Office & Welfare accommodation and Van loading canopies. Construction of new drivers’ facilities area including toilets, canteen, office, extended packing area and van loading canopies to include of a low level composite insulated panel clad storage, order picking and dispatch building and all associated works at Greenhills Road, Dublin 12, .

Current planning index: Granted. Read the linked decisions for their full terms.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    SD25A0139W

    Official source

  2. Planning decision

    SD25A0139W

    Permission granted

    Official source

  3. Grant date recorded

    SD25A0139W

    Official source

  4. Notified commencement

    CN0143598SD

    Phase 2 - The development shall consist of demolition of the existing centrally located two storey Office & Welfare accommodation and Van loading canopies. Construction of new drivers’ facilities area including toilets, canteen, office, extended packing area and van loading canopies to include of a low level composite insulated panel clad storage, order picking and dispatch building and all associated works at Greenhills Road, Dublin 12, .

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.