South Dublin County Council · SHD3ABP31250122 · Saggart, Dublin
Latest linked evidence
Notified commencement · 2024-12-19
SN0011740SD · Cairn Homes, has proposed the installation of a new standalone ESB(Electricity Supply Board) medium voltage (MV) substation at their residential development project located at Swift Banks, Adjacent to Swift Banks Manor Apartments, Mill Road, Saggart, Co. Dublin.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.
The proposed development at Swift Banks Manor, Mill Road, Saggart, Co. Dublin, is a five-story apartment building featuring two independent wings connected at the first and second floors. The building will house 118 apartment units across the ground to the fourth floors, comprising 34 one-bedroom (1-bed) units, 80 two-bedroom (2-bed) units, and 4 three-bedroom (3-bed) units. Additionally, the building will include plant and room amenities, as well as a bike store, all located on the ground floor.
118 units stated for this notice or phase; not a project total.
The proposed development at Swiftbanks View, Mill Road, Saggart, Co. Dublin, is a six-story residential building. This structure will feature a total of 59 apartment units, distributed from the ground to the fifth floor, consisting of 22 one-bedroom (1-bed) units and 37 two-bedroom (2-bed) units. Additionally, the building will include plant and room amenities, as well as bike stores, all located on the ground floor.
59 units stated for this notice or phase; not a project total.
Cairn Homes, has proposed the installation of a new standalone ESB(Electricity Supply Board) medium voltage (MV) substation at their residential development project located at Swift Banks, Adjacent to Swift Banks Manor Apartments, Mill Road, Saggart, Co. Dublin.
Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.
Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.