Dun Laoghaire Rathdown County Council · ABP30152218 · Dublin 18, Dublin
Latest linked evidence
Notified commencement · 2024-02-07
CN0109608DR · Construction of five apartment blocks consisting of 157 apartments in blocks ranging from 3 - 4 storeys above ground floor level. Each block is located above dedicated basement / undercroft car parking. Works include all landscaping, associated site services, enabling works and attenuation to all blocks at Clay Farm, Ballyogan Road, Dublin 18.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.
Source history
Timeline
Planning application received
ABP30152218
Grant date recorded
ABP30152218
Planning decision
ABP30152218
Permission granted
Notified commencement
CN0048346DR
Construction of 36 new dwellings at lands at Clay Farm, Ballyogan Road, Dublin 18.
Construction of 60 new dwellings at lands at Clay Farm, Ballyogan Road, Dublin 18. Planning permission is for 927 Residential Units and this Commencement Notice is for the first phase -60 Residential Dwellings
60 units stated for this notice or phase; not a project total.
Construction of five apartment blocks consisting of 157 apartments in blocks ranging from 3 - 4 storeys above ground floor level. Each block is located above dedicated basement / undercroft car parking. Works include all landscaping, associated site services, enabling works and attenuation to all blocks at Clay Farm, Ballyogan Road, Dublin 18.
157 units stated for this notice or phase; not a project total.
Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.
Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.