Latest linked evidence
Notified commencement · 2024-05-21
Sub-Station Stradbally: The construction a walled garden in the curtilage of Stradbally Hall: which is a protect structure (RPS No. 414): The creation of an opening in the southern wall of the walled garden. Construction of an ESB substation building. The substation building will accommodate client and medium voltage switchrooms and will be clad in stone in keeping with the adjoining existing wall and all associated site works.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.