Planning case FW18A0082

Fingal County Council · FW18A0082 · Huntstown, Dublin

Latest linked evidence

Notified commencement · 2019-06-10

Final Commencement Notice for Anaerobic Digester facility, Huntstown, Dublin 11 covering remaining ancillary buildings to be located within the site compound as follows: Security Kiosk - single story building located on site access route. Fire Hydrant Pump Room - single story building located to the North rear side of the Main building. MCC5 - single story building located to the West side of the Main building. MCC1 - single story building located to the East side of the Main building.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    FW18A0082

    Official source

  2. Planning decision

    FW18A0082

    Permission granted

    Official source

  3. Grant date recorded

    FW18A0082

    Official source

  4. Notified commencement

    Commencement notice

    WWTP Building for Anaerobic Digested facility, Huntstown, Dublin 11.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Final Commencement Notice for Anaerobic Digester facility, Huntstown, Dublin 11 covering remaining ancillary buildings to be located within the site compound as follows: Security Kiosk - single story building located on site access route. Fire Hydrant Pump Room - single story building located to the North rear side of the Main building. MCC5 - single story building located to the West side of the Main building. MCC1 - single story building located to the East side of the Main building.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.