Latest linked evidence
Notified commencement · 2025-10-28
Extension to the existing Baroda substation. The extension will consist of an enlarged compound of c. 198 m2, surrounded by a palisade fence with new gates. The extended compound will include the following: new c. 75m2 switchgear building (c.6m above ground/basement level), 2 No. 110kV/MV transformers and transformer bunds, 1 No. 15m high lightning monopole, 2 No. house transformers, surface water drainage with new attenuation tank and discharge to the public surface water sewer, internal roadway, cable ducting and installation, and all associated site works.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.