Save to pipeline
Connected planning records

Planning case 221457

Kildare County Council · 221457 · Newbridge, Kildare

Latest linked evidence

Notified commencement · 2025-10-28

Extension to the existing Baroda substation. The extension will consist of an enlarged compound of c. 198 m2, surrounded by a palisade fence with new gates. The extended compound will include the following: new c. 75m2 switchgear building (c.6m above ground/basement level), 2 No. 110kV/MV transformers and transformer bunds, 1 No. 15m high lightning monopole, 2 No. house transformers, surface water drainage with new attenuation tank and discharge to the public surface water sewer, internal roadway, cable ducting and installation, and all associated site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    221457

  2. Planning decision

    221457

    Conditional permission

  3. Grant date recorded

    221457

  4. Notified commencement

    Commencement notice

    Extension to the existing Baroda substation. The extension will consist of an enlarged compound of c. 198 m2, surrounded by a palisade fence with new gates. The extended compound will include the following: new c. 75m2 switchgear building (c.6m above ground/basement level), 2 No. 110kV/MV transformers and transformer bunds, 1 No. 15m high lightning monopole, 2 No. house transformers, surface water drainage with new attenuation tank and discharge to the public surface water sewer, internal roadway, cable ducting and installation, and all associated site works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.