~72 dwellings, Lands at Stonehaven Phase 2, Tipper West Blessington Road, Naas - Planning Application 2461085

Kildare County Council · 2461085 · Kildare

Latest linked evidence

Notified commencement · 2025-07-09

SN0012787KE · Terrace 14 will consist of 1 no. terrace consisting of 5 no. 2 story houses, each, with independent access at ground level, and a duplex to the end of the terrace. The duplex consists of a 1 no single storey apartment unit, with independent access at ground level, and 1 no. two storey maisonette unit accessed at first floor level via private external steps.

Indexed observation: Granted. Read the linked decisions for their full terms.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2461085

  2. Planning decision

    2461085

    Conditional permission

  3. Grant date recorded

    2461085

  4. Notified commencement

    CN0129915KE

    The development consists of the construction of 22no. Semi Detached houses, 2no. terraces of 5 units each and associated site works.

    32 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    SN0012781KE

    Terrace 4 will consist of 1 no. terrace consisting of 4 no. 2 story houses, each, with independent access at ground level, and a duplex to the end of the terrace. The duplex consists of a 1 no single storey apartment unit, with independent access at ground level, and 1 no. two storey maisonette unit accessed at first floor level via private external steps.

    6 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    SN0012782KE

    Terrace 6 will consist of 1 no. terrace consisting of 7 no. 2 story houses, each, with independent access at ground level, and a duplex to the end of the terrace. The duplex consists of a 1 no single storey apartment unit, with independent access at ground level, and 1 no. two storey maisonette unit accessed at first floor level via private external steps.

    9 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    SN0012783KE

    Terrace 7 will consist of 1 no. terrace consisting of 5 no. 2 story houses, each, with independent access at ground level, and a duplex to each end of the terrace. Each duplex consists of a 1 no single storey apartment unit, with independent access at ground level, and 1 no. two storey maisonette unit accessed at first floor level via private external steps.

    9 units stated for this notice or phase; not a project total.

    · Notice evidence

  8. Notified commencement

    SN0012786KE

    Terrace 12 will consist of 1 no. terrace consisting of 7 no. 2 story houses, each, with independent access at ground level, and a duplex to the end of the terrace. The duplex consists of a 1 no single storey apartment unit, with independent access at ground level, and 1 no. two storey maisonette unit accessed at first floor level via private external steps.

    9 units stated for this notice or phase; not a project total.

    · Notice evidence

  9. Notified commencement

    SN0012787KE

    Terrace 14 will consist of 1 no. terrace consisting of 5 no. 2 story houses, each, with independent access at ground level, and a duplex to the end of the terrace. The duplex consists of a 1 no single storey apartment unit, with independent access at ground level, and 1 no. two storey maisonette unit accessed at first floor level via private external steps.

    7 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.