Connected planning records

Planning case 2560532

Kilkenny County Council · 2560532

Latest linked evidence

Planning appeal received · 2026-08-26

501961

Open official source

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What is being built

Government document review

The exact Commission appeal 501961 was lodged on 26 August 2026 and is pending. These findings describe the July 2025 application EIAR; they do not establish the final appeal outcome, later revised details or new equipment orders.

3 official documents inspected · Checked 2026-09-05 · Official file index

The extension and the separate asphalt plant have different scopes

Proposed in application · Kilkenny 2560532: continued quarry use and the proposed lateral extension

What the evidence says
The July 2025 EIAR describes a 24.5 ha lateral extension: 18.2 ha of extraction and 6.3 ha of storage and screening berms. It explicitly excludes the independently operated asphalt plant from this application, while considering it for cumulative assessment.

Kilkenny 2560532: continued quarry use and the proposed lateral extension

Why it may matter — interpretation
Interpretation: keeps the extension, extraction footprint and neighbouring operation distinct.

What is not established
The current appeal outcome and any later amended footprint are not established.

Inspect the evidence

EIAR Chapter 3: Project Description · p.4
within an area of approx. 24.5 Ha. · Issued July 2025 (month only) · July 2025 application EIAR; received stamp dated 18 August 2025; received 2025-08-18 · Checked 2026-09-05

within an area of approx. 24.5 Ha.

The application proposes continued use of existing processing plant

Proposed in application · Processing for the proposed quarry extension; existing plant identified in the July 2025 EIAR

What the evidence says
The project description says the lateral extension uses the existing fixed and mobile crushing and screening plant. It states that no extra crushing or screening equipment is required. This is the applicant's proposed operating arrangement, not a new equipment purchase.

Processing for the proposed quarry extension; existing plant identified in the July 2025 EIAR

Why it may matter — interpretation
Interpretation: avoids treating a quarry extension as evidence of a new processing-plant order.

What is not established
Plant manufacturers, replacement work, procurement and current operational condition are not established.

Inspect the evidence

EIAR Chapter 3: Project Description · p.8
No extra crushing or screening equipment is required · Issued July 2025 (month only) · July 2025 application EIAR; received stamp dated 18 August 2025; received 2025-08-18 · Checked 2026-09-05

No extra crushing or screening equipment is required

The water report describes pumping, settlement and monitored discharge

Proposed in application · Existing quarry water management described in the July 2025 application

What the evidence says
The water chapter routes quarry water through a concrete tank sump and settlement ponds, with a hydrocarbon interceptor between the ponds. It describes a flume and ultrasonic flow meter at the discharge. The report proposes using this existing system for the extension; its capacity claim has not been independently certified here.

Existing quarry water management described in the July 2025 application

Why it may matter — interpretation
Interpretation: identifies the civil and monitoring systems while preserving their reported existing status.

What is not established
New pump or interceptor procurement, current certification and any appeal-imposed upgrade are not established.

Inspect the evidence

EIAR Chapter 8: Water · p.11
Flume Control structure and ultrasonic Flow Meter · Issued July 2025 (month only) · July 2025 application EIAR; received stamp dated 18 August 2025; received 2025-08-18 · Checked 2026-09-05

Flume Control structure and ultrasonic Flow Meter

The reported borehole supply serves operational water uses

Proposed in application · Reported existing water supply supporting proposed continued quarry use

What the evidence says
The water report describes a supply borehole averaging 350 cubic metres per day for offices, concrete batching, cooling, dust suppression and the wheelwash. It describes the existing wastewater system separately. This is reported operational supply, not a new mains connection or a newly approved abstraction quantity.

Reported existing water supply supporting proposed continued quarry use

Why it may matter — interpretation
Interpretation: separates operational water supply from wastewater infrastructure and proposed new work.

What is not established
Current measured demand, abstraction authorisation and a new water-system contract are not established.

Inspect the evidence

EIAR Chapter 8: Water · p.12
an average of 350m3/d · Issued July 2025 (month only) · July 2025 application EIAR; received stamp dated 18 August 2025; received 2025-08-18 · Checked 2026-09-05

an average of 350m3/d

The mitigation schedule specifies woodland and hedgerow works

Proposed in application · Application mitigation for the proposed quarry extension

What the evidence says
The July 2025 schedule proposes about 5.5 ha of mixed broadleaved woodland on screening berms, about 860 m of new native hedgerow and enhancement of about 300 m of existing hedgerow. These are different landscape measures, not one combined area or an installed planting schedule.

Application mitigation for the proposed quarry extension

Why it may matter — interpretation
Interpretation: identifies the proposed landscape package without combining unlike quantities.

What is not established
Final approved planting details, species quantities, procurement and completed planting are not established.

Inspect the evidence

EIAR Chapter 17: Mitigation and Monitoring · p.5
Approx. 5.5 ha of mixed broadleaved woodland · Issued July 2025 (month only) · July 2025 application EIAR; received stamp dated 18 August 2025; received 2025-08-18 · Checked 2026-09-05

Approx. 5.5 ha of mixed broadleaved woodland
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 3 government-published PDFs were visually inspected. The Commission page lists 30 PDF links. Selected pages from three chapters were visually inspected. The other chapters, appendices, council decision conditions and later appeal submissions have not been fully reviewed. Proposals do not establish procurement or installed work.

Source history

Timeline

  1. Planning application received

    2560532

  2. Planning decision

    2560532

    Conditional permission

  3. Planning appeal received

    501961

    Official source

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.