Planning case AA170488

Meath County Council · AA170488 · Ashbourne, Meath

Latest linked evidence

Notified commencement · 2018-11-08

CN0045786MH · Block C - No's 36-47 Churchfield Crescent, Churchfields, Ashbourne, Co. Meath - a three storey duplex block containing 12 units

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    AA170488

  2. Planning decision

    AA170488

    Conditional permission

  3. Grant date recorded

    AA170488

  4. Notified commencement

    CN0034907MH

    Construction of the 192 houses permitted under Reg. Ref. AA/170488 at Churchfields, Killegland, Ashbourne, Co. Meath

    192 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    CN0045782MH

    Block A - No's 16-23 Churchfield Crescent, Churchfields, Ashbourne, Co. Meath - a three storey duplex block containing 8 units

    8 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    CN0045785MH

    Block B - No's 24-35 Churchfield Crescent, Churchfields, Ashbourne, Co. Meath - a three storey duplex block containing 12 units

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    CN0045786MH

    Block C - No's 36-47 Churchfield Crescent, Churchfields, Ashbourne, Co. Meath - a three storey duplex block containing 12 units

    12 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.