Planning case D15A0841

Dun Laoghaire Rathdown County Council · D15A0841 · Booterstown, Dublin

Latest linked evidence

Notified commencement · 2016-06-21

CN0017468DR · Opt Out of Construction of single and two storey extension to front, side and rear, new entrance canopy to front, attic conversion with dormers to front and rear and velux rooflight to front. Alterations to elevations to include new render and brick finish. Provision of solar panels on roof to rear and side. Existing vehicular access to front to be widened to include provision of new gates. All including any associated siteworks to an existing semi-detached two storey house at 137 Booterstown Avenue, Booterstown, Co. Dublin.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    D15A0841

  2. Planning decision

    D15A0841

    Permission granted

  3. Grant date recorded

    D15A0841

  4. Notified commencement

    CN0017468DR

    Opt Out of Construction of single and two storey extension to front, side and rear, new entrance canopy to front, attic conversion with dormers to front and rear and velux rooflight to front. Alterations to elevations to include new render and brick finish. Provision of solar panels on roof to rear and side. Existing vehicular access to front to be widened to include provision of new gates. All including any associated siteworks to an existing semi-detached two storey house at 137 Booterstown Avenue, Booterstown, Co. Dublin.

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.