Save this project to account
Connected planning records

Planning case 2560008

Mayo County Council · 2560008 · Ballina, Mayo

Latest linked evidence

Notified commencement · 2026-06-30

CN0144633MO · Construction of a housing development with a total of 50 no. dwellings in detached, semi-detached and terrace configurations, consisting of 19 no. 5-bed detached houses, 6 no. 4-bed semi-detached houses, 2 no. 3-bed semi-detached houses, 1 no. 3-bed detached house, 10 no. 3-bed terrace houses, 11 no. 2-bed terrace houses and 1 no. 2 bed detached single storey house. Associated development and works including the extension of existing pedestrian and vehicular access to Lansyn Bohernasup, all hard and soft landscaping, internal roads and footpaths, cycle and car parking, public and private amenities and open spaces, boundary treatments, public lighting, and all other ancillary works above and below ground including connections to water supply, surface water infrastructure, wastewater infrastructure and utilities.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2560008

  2. Planning decision

    2560008

    Conditional permission

  3. Notified commencement

    CN0144633MO

    Construction of a housing development with a total of 50 no. dwellings in detached, semi-detached and terrace configurations, consisting of 19 no. 5-bed detached houses, 6 no. 4-bed semi-detached houses, 2 no. 3-bed semi-detached houses, 1 no. 3-bed detached house, 10 no. 3-bed terrace houses, 11 no. 2-bed terrace houses and 1 no. 2 bed detached single storey house. Associated development and works including the extension of existing pedestrian and vehicular access to Lansyn Bohernasup, all hard and soft landscaping, internal roads and footpaths, cycle and car parking, public and private amenities and open spaces, boundary treatments, public lighting, and all other ancillary works above and below ground including connections to water supply, surface water infrastructure, wastewater infrastructure and utilities.

    50 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.