Planning case F19A0120

Fingal County Council · F19A0120 · Sutton, Dublin

Latest linked evidence

Notified commencement · 2019-07-22

A new interim primary school opening in September 2019 and this start-up accommodation is required to enable the school to commence operation. The development will consist of the provision of a temporary primary school by way of construction of 1 no. prefabricated buildings within a defined enclosed site

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    F19A0120

    Official source

  2. Planning decision

    F19A0120

    Permission granted

    Official source

  3. Grant date recorded

    F19A0120

    Official source

  4. Notified commencement

    Commencement notice

    A new interim primary school opening in September 2019 and this start-up accommodation is required to enable the school to commence operation. The development will consist of the provision of a temporary primary school by way of construction of 1 no. prefabricated buildings within a defined enclosed site

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.