Connected planning records

Planning case 2260966

Galway County Council · 2260966 · Tuam, Galway

Latest linked evidence

Notified commencement · 2024-01-22

Construction of new entrance onto existing private estate road including alterations to existing footpath. Construction of boundary fencing and walls. Stripping back topsoil and filling to tank and yard area. Provision of service connections including water, sewer & electricity. Installation of overground fuel storage tanks including associated pipework. Installation of stormwater drainage systems and surfacing. Construction of electrical cabinet (3.5 sq.m) (Building to be commenced under separate commencement notice)

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2260966

  2. Planning decision

    2260966

    Conditional permission

  3. Grant date recorded

    2260966

  4. Notified commencement

    Commencement notice

    Construction of new entrance onto existing private estate road including alterations to existing footpath. Construction of boundary fencing and walls. Stripping back topsoil and filling to tank and yard area. Provision of service connections including water, sewer & electricity. Installation of overground fuel storage tanks including associated pipework. Installation of stormwater drainage systems and surfacing. Construction of electrical cabinet (3.5 sq.m) (Building to be commenced under separate commencement notice)

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.