Save this project to account
Connected planning records

Planning case 20696

Louth County Council · 20696 · Earlsfort, Louth

Latest linked evidence

Notified commencement · 2024-09-23

Construction of 18 No. Dwelling Units C1-C18 at Clara, Earlsfort Blackrock Co Louth and all associated site development works

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    20696

  2. Planning decision

    20696

    Conditional permission

  3. Grant date recorded

    20696

  4. Notified commencement

    Commencement notice

    Dwelling No.s A43+A44, A45+A46, A47+A48, A55+A56, A57+A58, A83 + A84 and A85 + A86 Adare, Earlsfort, Blackrock, Co. Louth.

    14 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of dwelling Units A49+A50, A51, A52+A53+A54, A59+A60+A61, A78+A79+80, A81+82 and A87+88 at Adare, Ealsfort, Blackrock, Co. Louth and all associated site development works.

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of 3 storey residential building of 6 No. Apartments, 3 No. 1 bed apartments at ground floor and 3 No. 3 bed duplex apartments over and associated site works.

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Dwelling No.s A62+A63, A64+A65, A66+A67, A68+A69, A70+A71 Adare Earlsfort Blackrock Co Louth

    10 units stated for this notice or phase; not a project total.

    · Notice evidence

  8. Notified commencement

    Commencement notice

    Construction of 14 No Dwelling Houses (No. A1, A2, A3, A4, A33+34, A35,A36+A37, A38+A39, A40,A41+A42 Adare, Earlsfort, Blackrock, Co. Louth)

    14 units stated for this notice or phase; not a project total.

    · Notice evidence

  9. Notified commencement

    Commencement notice

    Construction of dwellings No. R1, R2+R3, R4+R5, R6+R7, R8 at Rossmore, Earlsfort, Blackrock and all associated site development works

    8 units stated for this notice or phase; not a project total.

    · Notice evidence

  10. Notified commencement

    Commencement notice

    Construction of dwelling Units R9+R10, R11+12, R13+R14, R15+R16, R17+R18, R19+R20, R21+R22, R23+R24, R25+R26, R27+R28 and R29+R30 at Rossmore, Earlsfort, Blackrock, Co. Louth and all associated site development works

    65 units stated for this notice or phase; not a project total.

    · Notice evidence

  11. Notified commencement

    Commencement notice

    Construction of dwelling Units R50+R51, R52+R53, R54+R55 and R56+R57 at Rossmore, Earlsfort, Blackrock, Co. Louth and all associated site development works.

    8 units stated for this notice or phase; not a project total.

    · Notice evidence

  12. Notified commencement

    Commencement notice

    11 No. Dwelling Units, 5 No. at Adare A6+A8, A10+A11+A12 and 6 No. at Rossmore R84 and R85-R89, Earlsfort, Blackrock, Co Louth and all associated development works.

    11 units stated for this notice or phase; not a project total.

    · Notice evidence

  13. Notified commencement

    Commencement notice

    Construction of 18 No. Dwelling Units C1-C18 at Clara, Earlsfort Blackrock Co Louth and all associated site development works

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.