Planning case 1851993

Donegal County Council · 1851993 · Letterkenny, Donegal

Latest linked evidence

Notified commencement · 2024-10-12

Construction of a new building containing 4 No.apartments - 01, 02, 03 & 04 at An Chraobh Bheag, Creeve Smith, Letterkenny, Co. Donegal.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    1851993

  2. Planning decision

    1851993

    Conditional permission

  3. Grant date recorded

    1851993

  4. Notified commencement

    Commencement notice

    Construction of apartment block containing Nos. 30,31,32 & 33 (4 No. apartments) at Crieve Mór Avenue, Crievesmith, Letterkenny. (4817)

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of apartment block at Nos. 65,66,67 & 68 Crieve Mór Avenue, Crievesmith, Letterkenny. (4817)

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of a new building containing 4 No.apartments 05,06,07 & 08 at An Chraobh Bheag, Creeve Smith, Letterkenny, Co. Donegal

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Construction of a new building containing 4 No.apartments - 01, 02, 03 & 04 at An Chraobh Bheag, Creeve Smith, Letterkenny, Co. Donegal.

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.