Planning case WEB154520

Dublin City Council · WEB154520 · Inchicore, Dublin

Latest linked evidence

Notified commencement · 2023-05-26

The development will consist of the demolition of a vacant, end-of- terrace shop unit to allow for the construction of 2 no. townhouse type dwellings. Together, these will approximate the existing building envelope but will include front porches and ground floor extensions to the rear to make space for living, kitchen, and dining uses. The first floor and attic level will consist of a total 3 no. bedrooms in each unit, the uppermost of which will be contained under a new pitched roof with dormer windows to the rear. The front and rear outdoor spaces will serve as private outdoor gardens.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    WEB154520

  2. Planning decision

    WEB154520

    Permission granted

  3. Grant date recorded

    WEB154520

  4. Notified commencement

    Commencement notice

    The development will consist of the demolition of a vacant, end-of- terrace shop unit to allow for the construction of 2 no. townhouse type dwellings. Together, these will approximate the existing building envelope but will include front porches and ground floor extensions to the rear to make space for living, kitchen, and dining uses. The first floor and attic level will consist of a total 3 no. bedrooms in each unit, the uppermost of which will be contained under a new pitched roof with dormer windows to the rear. The front and rear outdoor spaces will serve as private outdoor gardens.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.