Notified commencement · 2021-05-24

Extension of the existing Aldi store increasing the gross floor area from 1,553 sq.m. to 2,148 sq.m., 500 sq.m. extension to the existing single storey retail area with additional 65 sq.m. extension to warehouse and 22 sq.m. extension to provide an ancillary meeting room. New store entrance/exit with canopy to replace the existing (south east elevation). Demolition of existing wall and curtain walling entrance in retail area to allow for extension and associated site works at existing Aldi Store, Dublin Road, Cavan, Co. Cavan.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    18271

  2. Planning decision

    18271

    Conditional permission

  3. Grant date recorded

    18271

  4. Notified commencement

    Commencement notice

    Extension of the existing Aldi store increasing the gross floor area from 1,553 sq.m. to 2,148 sq.m., 500 sq.m. extension to the existing single storey retail area with additional 65 sq.m. extension to warehouse and 22 sq.m. extension to provide an ancillary meeting room. New store entrance/exit with canopy to replace the existing (south east elevation). Demolition of existing wall and curtain walling entrance in retail area to allow for extension and associated site works at existing Aldi Store, Dublin Road, Cavan, Co. Cavan.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.