Planning case 19466

Cavan County Council · 19466 · Ballyconnell, Cavan

Latest linked evidence

Notified commencement · 2020-04-20

SN0005257CN · Construction of (a) lean-to extension to side (southwest) of existing factory incorporating offices (147sqm) (b) alterations to existing layout which includes relocating workshop (31sqm) (excludes works carried out to date including removal of walls/first floor, foundations to office extension, relocated canteen (45sqm) and saw workshop (52sqm) (c) change of use of existing office area to retail outlet (47sqm)(excludes alterations carried out to elevations to date)at existing wood processing facility.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    19466

  2. Planning decision

    19466

    Conditional permission

  3. Grant date recorded

    19466

  4. Notified commencement

    SN0005257CN

    Construction of (a) lean-to extension to side (southwest) of existing factory incorporating offices (147sqm) (b) alterations to existing layout which includes relocating workshop (31sqm) (excludes works carried out to date including removal of walls/first floor, foundations to office extension, relocated canteen (45sqm) and saw workshop (52sqm) (c) change of use of existing office area to retail outlet (47sqm)(excludes alterations carried out to elevations to date)at existing wood processing facility.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.