Save this project to account
Connected planning records

Planning case 234602

Cork County Council · 234602 · Midleton, Cork

Latest linked evidence

Notified commencement · 2025-02-25

The construction of a new client-side single storey electrical substation building and associated site development works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    234602

    Official source

  2. Planning decision

    234602

    Conditional permission

    Official source

  3. Grant date recorded

    234602

    Official source

  4. Notified commencement

    Commencement notice

    Construction of a Brewhouse Building for the expansion of the Irish Distillers facility at Midleton, Co Cork

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of a Wash and Grain Column Building for the expansion of the Irish Distillers facility at Midleton, Co. Cork, . The building is an industrial building with a relatively low occupancy consisting of able- bodied staff members and maintenance.

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of a Pot Stillhouse Building for the expansion of the Irish Distillers facility at Midleton, Co. Cork

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Construction of a new Pot Stillhouse MVR building for the expansion of the Irish Distillers Facility at Midleton, Co. Cork, . The Building is an industrial building with low occupancy consisting of able-bodied staff members for maintenance.

    Quantity not established for this notice.

    · Notice evidence

  8. Notified commencement

    Commencement notice

    The construction of a new ESB-side single storey electrical substation buildings and associated site development works.

    Quantity not established for this notice.

    · Notice evidence

  9. Notified commencement

    Commencement notice

    The construction of a new client-side single storey electrical substation building and associated site development works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.