Connected planning records

Planning case SD16A0088

South Dublin County Council · SD16A0088 · Clondalkin, Dublin

Latest linked evidence

Notified commencement · 2020-09-16

Development will comprise of 1no. single storey data centre (DUB13) located south of data centres DUB09, DUB10 & DUB12, to include all ancillary site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    SD16A0088

    Official source

  2. Planning decision

    SD16A0088

    Permission granted

    Official source

  3. Grant date recorded

    SD16A0088

    Official source

  4. Notified commencement

    Commencement notice

    Development will comprise 1 no. single storey data centres (DUB09) located west of data centres DUB06, DUB07 & DUB08. Gross floor area c.17,598 sq.m. The height of the building will range between c.6.1m & c.13.3m high. Ancillary site works for connection to infrastructural services, as well as fencing, landscaping, perimeter service roads around the building. 52 no. additional operational parking spaces (including 3 no. universal accessible spaces). Provision of 5 no. bicycle parking spaces. All associated site development, service provision, landscaping and associated works.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Development will comprise 1 no. single storey data centres (DUB10) located west of data centres DUB06, DUB07 & DUB08. Gross floor area c.17,598 sq.m. The height of the building will range between c.6.1m & c.13.3m high. Ancillary site works for connection to infrastructural services, as well as fencing, landscaping, perimeter service roads around the building. 49 no. additional operational parking spaces (including 3 no. universal accessible spaces). Provision of 5 no. bicycle parking spaces. All associated site development, service provision, landscaping and associated works.

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Development will comprise of 1 no. single storey data centre (DUB12) located south of data centres DUB09 & DUB10, to include all ancillary site works.

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Development will comprise of 1no. single storey data centre (DUB13) located south of data centres DUB09, DUB10 & DUB12, to include all ancillary site works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.