Save this project to account
Connected planning records

Planning case D22B0393

Dun Laoghaire Rathdown County Council · D22B0393 · Dublin, Dublin

Latest linked evidence

Notified commencement · 2023-03-20

A) Demolition of the existing rear, ground-floor, flat-roofed utility, bathroom and side garage. b) Construction of a rear, ground floor, flat-roofed extension with roof-lights. c) Reconstruction of the side, integrated flat-roofed garage as habitable accommodation with a front window and roof-lights, including raising the height of the flat roof to same to give level access from the house. d) Associated site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    D22B0393

  2. Planning decision

    D22B0393

    Permission granted

  3. Grant date recorded

    D22B0393

  4. Notified commencement

    Commencement notice

    a) Demolition of the existing rear, ground-floor, flat-roofed utility, bathroom and side garage. b) Construction of a rear, ground floor, flat-roofed extension with roof-lights. c) Reconstruction of the side, integrated flat-roofed garage as habitable accommodation with a front window and roof-lights, including raising the height of the flat roof to same to give level access from the house. d) Associated site works.

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.