Save this project to account
Connected planning records

Planning case 19218

Offaly County Council · 19218 · Tullamore, Offaly

Latest linked evidence

Notified commencement · 2020-02-18

The development will consist of (i) Extension of existing E-Building to cover footprint of yard in front of existing E-Building, and associated site works. Floor area of proposed extension = 870sq.m, Maximum Height = 11.6m; and (ii) Extension of existing D-Hanger Building to cover footprint of existing yard in front of D-Hanger Building, and associated site works; Floor area of proposed extension = 235sq.m; Maximum Height = 11.1m; The facility operates under Waste Licence No. W0113-04, and Industrial Emissions Licence (Main Class of Activity 11.2 (f)).

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    19218

  2. Planning decision

    19218

    Conditional permission

  3. Grant date recorded

    19218

  4. Notified commencement

    Commencement notice

    The development will consist of (i) Extension of existing E-Building to cover footprint of yard in front of existing E-Building, and associated site works. Floor area of proposed extension = 870sq.m, Maximum Height = 11.6m; and (ii) Extension of existing D-Hanger Building to cover footprint of existing yard in front of D-Hanger Building, and associated site works; Floor area of proposed extension = 235sq.m; Maximum Height = 11.1m; The facility operates under Waste Licence No. W0113-04, and Industrial Emissions Licence (Main Class of Activity 11.2 (f)).

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.