Connected planning records

Planning case 2561246

Limerick City and County Council · 2561246

Latest linked evidence

Planning appeal received · 2026-08-17

501898

Open official source

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What is being built

Government document review

The 4 August 2026 council decision follows the 13 July heritage/ecology submission; Commission case 501898 is pending after lodging on 17 August. The original November drainage design and the separate wildlife-licence window remain explicitly dated.

3 official documents inspected · Checked 2026-09-06 · Official file index

The event-centre decision is under appeal

Council decision under appeal; implementation not established · Limerick 2561246; event centre and separate existing outbuilding refurbishment

What the evidence says
The council notified a decision to grant on 4 August 2026 after further information received on 13 July. The decision describes an approximately 1,460 m² event centre and separate refurbishment of the existing 22 m² Building 12, within the Roche Castle setting. Commission case 501898 records an appeal lodged on 17 August and no decision. This is a staff event and training facility on the existing campus, not a new pharmaceutical production building or a final grant.

Limerick 2561246; event centre and separate existing outbuilding refurbishment

Why it may matter — interpretation
Interpretation: keeps the current consent stage and work package distinct from the wider production campus.

What is not established
The appeal outcome, final grant, commencement and completed floor area remain unverified.

Inspect the evidence

Regeneron event centre: notification of decision to grant · p.1
approximately 1,460.0 square meters · Issued 2026-08-04 · Eight conditions; incorporates the 13 July further-information submission; explicitly not a final grant · Checked 2026-09-06

approximately 1,460.0 square meters

The original design names AquaCell NG or equivalent

Source-specific proposal; final detail and implementation unverified · November Issue A design for the event-centre drainage; two location-specific tanks

What the evidence says
The November infrastructure report specifies two soakaway tanks: a stated 55 m³ beneath the car park and 83 m³ beneath the adjoining green area. Its calculation basis is Wavin AquaCell NG or equivalent with permeable geotextile and 96% void space. These are separate stated design volumes and an example product basis, not an order or a verified installed capacity. The report predates the July heritage and ecology response; the complete later drawing set has not been reconciled.

November Issue A design for the event-centre drainage; two location-specific tanks

Why it may matter — interpretation
Interpretation: retains a useful named drainage system without turning an equivalent specification into a selected supplier.

What is not established
Final tank geometry, hydraulic acceptance, chosen product and installed volumes are unverified.

Inspect the evidence

Regeneron castle conversion: site infrastructure planning report · p.9
Wavin Aquacell NG (or equivalent) · Issued 2025-11-28 · Issue A; IE0313575-30-RP-0001; original design with calculation appendices · Checked 2026-09-06

Wavin Aquacell NG (or equivalent)

The proposal keeps this roof runoff out of the canal

Source-specific proposal; final detail and implementation unverified · Event-centre and courtyard roof catchment; wider campus drainage excluded

What the evidence says
The infrastructure report proposes gutters and downpipes to the existing courtyard roofs and the new event-centre roof, feeding a dedicated infiltration network. The scheme includes 225–300 mm twinwall carrier pipes, gullies, channels and permeable paving. Both the original report and the August decision describe two soakaways and no discharge from this building to the Loughmore Canal. This is the specified route for this package, not a claim about all campus drainage or proven discharge performance.

Event-centre and courtyard roof catchment; wider campus drainage excluded

Why it may matter — interpretation
Interpretation: explains how the existing roofs and new works connect to a defined civil-engineering package.

What is not established
Later detailed pipe layouts, site testing, installed network and actual discharge performance are unverified.

Inspect the evidence

Regeneron castle conversion: site infrastructure planning report · p.8
No water is leaving the site · Issued 2025-11-28 · Issue A; IE0313575-30-RP-0001; original design with calculation appendices · Checked 2026-09-06

No water is leaving the site

Regeneron castle conversion: site infrastructure planning report · p.9
225mm to 300mm · Issued 2025-11-28 · Issue A; IE0313575-30-RP-0001; original design with calculation appendices · Checked 2026-09-06

225mm to 300mm

Foul drainage connects to the existing campus pumping system

Source-specific proposal; final detail and implementation unverified · November proposed event-centre foul network and existing private pump chamber

What the evidence says
The November report proposes mainly 150 mm gravity foul drainage serving three vendor units, a breakroom and two toilet areas. It connects to an existing foul pump chamber, with a macerator added to the existing pumps. The report does not propose a new direct public-sewer discharge for this development. This is an interface with the campus system, not a new standalone treatment plant.

November proposed event-centre foul network and existing private pump chamber

Why it may matter — interpretation
Interpretation: identifies the specific pump and drainage interface without expanding it to the entire campus.

What is not established
Final pump duty, macerator model, approved detailed design and commissioning are unverified.

Inspect the evidence

Regeneron castle conversion: site infrastructure planning report · p.10
A macerator shall be incorporated · Issued 2025-11-28 · Issue A; IE0313575-30-RP-0001; original design with calculation appendices · Checked 2026-09-06

A macerator shall be incorporated

The decision requires a salvage catalogue and conservation oversight

Council decision under appeal; implementation not established · Council conditions 3 and 4; protected courtyard buildings and their interfaces

What the evidence says
Condition 3 requires a catalogue of salvaged fabric and features placed in storage for potential reuse, with an alternative strategy if reuse within the site is unlikely. Condition 4 requires qualified architectural-conservation supervision and a completion record. The July response had addressed doors and windows, mechanical and electrical routes, and the new-to-existing roof connection. A catalogue requirement does not establish that each stored item will be reused.

Council conditions 3 and 4; protected courtyard buildings and their interfaces

Why it may matter — interpretation
Interpretation: shows the conservation and reuse obligations attached to the works.

What is not established
The final item-by-item reuse destinations, completed conservation works and compliance submission are not verified.

Inspect the evidence

Regeneron event centre: notification of decision to grant · p.3
potential future reuse · Issued 2026-08-04 · Eight conditions; incorporates the 13 July further-information submission; explicitly not a final grant · Checked 2026-09-06

potential future reuse

Further-information response and wildlife licence: first indexed PDF · p.4
Mechanical and Electrical services · Issued 2026-07-10 · Cover letter dated 10 July, received 13 July; appended NPWS licence signed 8 July. First of four files in the indexed submission. · Checked 2026-09-06

Mechanical and Electrical services

The submitted wildlife licence has a separate end date

Source-specific proposal; final detail and implementation unverified · Submitted NPWS licence conditions; separate statutory permission and timing

What the evidence says
The July submission contains a wildlife derogation signed on 8 July 2026. Its conditions limit the authorised actions to 8 July–31 December 2026, require ecological supervision, and expressly prevent works under it before planning permission is granted. That ecological permission is separate from the pending planning appeal; it is not evidence that construction is authorised now or that the licence window will be extended.

Submitted NPWS licence conditions; separate statutory permission and timing

Why it may matter — interpretation
Interpretation: keeps an expiry-sensitive enabling permission separate from the planning decision.

What is not established
A later licence extension, final planning permission and completed authorised actions have not been established.

Inspect the evidence

Further-information response and wildlife licence: first indexed PDF · p.7
8th July – 31st December 2026 · Issued 2026-07-10 · Cover letter dated 10 July, received 13 July; appended NPWS licence signed 8 July. First of four files in the indexed submission. · Checked 2026-09-06

8th July – 31st December 2026
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 3 government-published PDFs were visually inspected. Fifty-four council index rows were retained. Selected pages of three supporting PDFs were visually inspected; a fourth downloaded planning report was text-screened only. The first of four files in the further-information submission was inspected, not the entire submission or all hydraulic appendices. Proposals do not establish procurement or installed work.

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.