Save this project to account
Connected planning records

Planning case 2460317

Kilkenny County Council · 2460317 · Mooncoin, Kilkenny

Latest linked evidence

Notified commencement · 2024-12-23

CN0123731KK · for changes to previously granted under planning permission ref no. 21/225 for the construction of a masonary detached dwelling house, site entrance and all associated site works, to include changes to house design, changes to site boundaries, changes to works proposed to neighbouring properties including decommissioning of existing septic tank on neighbouring site and installation of a new domestic waste water treatment system, percolation area and all associated site works

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2460317

  2. Planning decision

    2460317

    Conditional permission

  3. Grant date recorded

    2460317

  4. Notified commencement

    CN0123730KK

    Construction of a detached masonary domestic garage

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    CN0123731KK

    for changes to previously granted under planning permission ref no. 21/225 for the construction of a masonary detached dwelling house, site entrance and all associated site works, to include changes to house design, changes to site boundaries, changes to works proposed to neighbouring properties including decommissioning of existing septic tank on neighbouring site and installation of a new domestic waste water treatment system, percolation area and all associated site works

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.