Planning case FW13A0097

Fingal County Council · FW13A0097 · Ballycoolin, Dublin

Latest linked evidence

Notified commencement · 2014-08-20

CN0001795FL · The development consists of the provision for a new entrance gate and turnstile at the existing site entrance, new gate substation at the northwest corner of the site, 2,294sq.m. of new data hall space and associated areas, 2,112sq.m. of a single and two storey plant enclosure to the south and east of the existing building, a 9.0m high roof mounted telecoms tower at the southeast corner of the proposed extension, landscaping and all associated site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    FW13A0097

    Official source

  2. Planning decision

    FW13A0097

    Permission granted

    Official source

  3. Grant date recorded

    FW13A0097

    Official source

  4. Notified commencement

    CN0001795FL

    The development consists of the provision for a new entrance gate and turnstile at the existing site entrance, new gate substation at the northwest corner of the site, 2,294sq.m. of new data hall space and associated areas, 2,112sq.m. of a single and two storey plant enclosure to the south and east of the existing building, a 9.0m high roof mounted telecoms tower at the southeast corner of the proposed extension, landscaping and all associated site works.

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.