Latest linked evidence
Notified commencement · 2026-07-07
CN0144740FL · a) Construction of three new substations, standalone with a total area of 118sqm, at rear of the existing Server Buildings 2,3 and 6 at the IBM Technology Campus. b) Demolition of the three existing corridor links between server buildings 2 and 3. c) New external cladding and doors to match existing finishes d) Demolition of existing substation standalone at southeast side e) Site wide underground utilities upgrade works. f) Landscape alterations to the areas where existing corridor links were demolished, to be replaced with hard landscaping
Current planning index: Granted. Read the linked decisions for their full terms.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.