Protected structure, 53, Kenilworth Square South, Dublin 6 - Planning Application 3545/24

Dublin City Council · 354524 · Dublin

Latest linked evidence

Notified commencement · 2025-07-08

Reconstruction of existing upper ground floor extension to the rear, construction of a new two storey extension to the rear, new outdoor terrace to the rear at upper ground floor level, with steps down to back garden level, internal alterations, relocation of the side door on the East façade, new rooflight to the rear, removal of existing shed, construction of a new shed in the back garden and all associated site works at 53 Kenilworth Square South, Dublin 6 (a Protected Structure).

Indexed observation: Granted. Read the linked decisions for their full terms.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    354524

  2. Planning decision

    354524

    Permission granted

  3. Grant date recorded

    354524

  4. Notified commencement

    Commencement notice

    Reconstruction of existing upper ground floor extension to the rear, construction of a new two storey extension to the rear, new outdoor terrace to the rear at upper ground floor level, with steps down to back garden level, internal alterations, relocation of the side door on the East façade, new rooflight to the rear, removal of existing shed, construction of a new shed in the back garden and all associated site works at 53 Kenilworth Square South, Dublin 6 (a Protected Structure).

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.