PHASE 1 of a material alteration and change of use to construct
(bounded by Parnell Street, King's Inn Street and Loftus Lane), Dublin · Dublin
- Commencement date
- 2018-10-01
- Planning reference
- 3334/17
- Planning authority
- Dublin City Council
- Project type
- Material alteration · Change of use
- Floor area
- 1382 m² · per notice; not summed
- Indexed source check
- 2026-06-09T15:11:14Z
Works description
PHASE 1 of a material alteration and change of use to construct a new microbrewery & visitor centre at 5/6 & 7/8 Parnell Centre, Dublin 1. This phase consist of modifcations to the existing below ground drainage, floor levels and associated works within the units and common areas in the demise of the Parnell Centre. Planning permission with grant order nos P3033 & P3549 are applicable to the entire development. An effluent discharge license, Ref no 916889 has been applied for this development.
This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.