The fit-out of an existing Data Centre located in Blanchardstown

Dublin 15, Dublin · Dublin

Commencement date
2022-05-12
Planning reference
FW22A/0011
Planning authority
Fingal County Council
Project type
Material alteration
Floor area
706 m² · per notice; not summed
Indexed source check
2026-06-09T15:11:14Z

Works description

The fit-out of an existing Data Centre located in Blanchardstown Corporate Park, Dublin 15 as part of Phase 2 works. Phase 1 works were commenced under a Short Form Commencement Notice (Ref No: ). Phase 2 comprises data hall fit out works to an area measuring 455 m2, with an IT load of 1.4 MW, plant in external compound, associated support service on gantry level and 2 no. standby generators with associated flues, server and plant rooms at ground floor and customer room on the first floor with and IT load of 50kw.

This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.