Phase 02 Construction of Piling Only to Andrews Lane Theatre
Dublin 2, Dublin · Dublin
- Source notice reference
- CN0042725DC
- Commencement date
- 2018-08-22
- Planning reference
- 4342/16
- Planning authority
- Dublin City Council
- Project type
- New build
- Floor area
- 3586 m² · per notice; not summed
- Builder company
- Duggan Brothers (Contractors) Ltd
- Developer company
- Andrew'S Lane Development Ltd
- Indexed source check
- 2026-06-09T15:11:14Z
Public-safe works description
Phase 02 Construction of Piling Only to Andrews Lane Theatre (The ALT) Hotel Project. This work to be carried out in advance of a new build Hotel Project (All remaining works) to be submitted under a separate additional CN application (Phase 03). Andrew's Lane Theatre, 9-17 Saint Andrew's Lane, Dublin 2.
This is one source-family notice identity, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.