Infrastructure · Co. Carlow

Powerstown, Milford, Co. Carlow

Granted on appeal 22 Jul 2026 (Granted 25 Feb 2026 by the council)

This permission is final and the work is already built, so there is nothing more to email you about. Get new planning applications in Milford by email

Key facts

  • Planning application 2560436 at Powerstown, Milford, Co. Carlow: Retention of.
  • It was received by Carlow County Council on 23 Dec 2025.
  • Status: Granted on appeal 22 Jul 2026 (Granted 25 Feb 2026 by the council).
  • Permission to retain the work was granted on appeal on 22 Jul 2026; the board's decision is final. The work is already built, so no site start is expected.

Source: the Carlow County Council planning register, checked 2 Jun 2026. Open the council's file

More planning applications in Milford · Planning applications in Co. Carlow

What and where

Retention of

Retention permission the retention of: a rock splitter and associated ancillary canopy covering an area of c. 120.1 m² with a maximum height of c. 7.2m and associated single storey cabin/site office measuring c. 4.7 m² in area; aggregate washing plant with a maximum height of c. 10.7m; welding shed measuring c. 190.2 m² in area with a maximum height of c. 8.4m; and Electricity Supply Board substation measuring c. 13.5 m² in area with a maximum height of c. 3.2m. Retention is also sought for all associated ancillary site development works, including site levelling, lighting, cabling and ducting

Description as published by the council. Its text starts part-way through a sentence.

Location
Milford, Co. Carlow Map
Planning reference
2560436
Application type
Retention permissionPermission to keep work already carried out.

Numbers and dates

Floor area
328 m²
Project type
Infrastructure
Received
23 Dec 2025
Council decision
25 Feb 2026
Appeal lodged
5 Mar 2026
Granted on appeal
22 Jul 2026

Timeline

  1. Application received
  2. Granted by the council
  3. Appeal lodged
  4. Appeal decidedGrant permission

Site history

This site's history

  1. Application 2660212 at the same address: received 10 Jul 2026, no decision recorded yet.

    the construction of portal frame curing shed for pre-cast concrete products and associated site works Same address

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Permission to retain the work was granted on appeal on 22 Jul 2026; the board's decision is final. The work is already built, so no site start is expected.

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Carlow County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near Milford

Get alerts for MilfordFree. We email you when new applications appear.

Free email alerts

Get new Milford projects by email

New applications, decisions and site starts in Milford, Co. Carlow. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options