Save to pipeline

Planning application · Co. Clare

Development will consist of, Co. Clare

Refused 23 Oct 2024

What and where

Development will consist of

The development will consist of: (i) The construction of 7 no. wind turbines with the following parameters: a. Total tip height range of 179.5m – 180m, b. Rotor diameter range of 149m – 155m, c. Hub height range of 102.5m to 105m, (ii) Construction of associated foundations, hardstand and assembly areas; (iii) All associated wind farm underground electrical and communications cabling connecting the turbines and mast to the proposed electrical substation; (iv) Construction of 1 no. permanent 38kV electrical substation including a single-story control building with welfare facilities, all associated electrical plant and equipment, security fencing, entrance on to new access road, all associated internal underground cabling, drainage infrastructure, wastewater holding tank, retention separator tank, and all ancillary works, in the townland of Killeagy (Goonan), Co. Clare; (v) A Battery Energy Storage System within the 38kV electrical substation compound; (vi) 1 no. permanent meteorological mast of c. 36.5m in height, associated foundation and hard-standing area in the townland of Shannaknock; (vii) The permanent upgrade of 1 no. existing site entrance off the L7080 (‘The Gap Road’) for the provision of construction and operational access; (viii) Provision of 3 no. new permanent site entrances off the L7080 for the provision of construction and operational access; (ix) Provision of 3 no. new temporary site entrances off the L7080 for the provision of construction access; (x) Upgrade of existing tracks/ roads, including the L7080, and the provision of new site access roads, 4 no. watercourse crossings, junctions and hardstand areas; (xi) 1 no. temporary construction compound with temporary offices and staff facilities in the townland of Killeagy (Goonan); (xii) 1 no. temporary storage area in the townland of Killeagy (Goonan); (xiii) 1 no. borrow pit in the townland of Killeagy (Goonan); (xiv) Peat and Spoil Management; (xv) Tree Felling to accommodate the construction and operation of the proposed development; (xvi) Operational stage site and amenity signage; and (xvii) All ancillary apparatus and site development works above and below ground, including soft and hard landscaping and drainage infrastructure. A 10-year planning permission and 35-year operational life of the wind farm from the date of commissioning of the entire wind farm is sought. A Design Flexibility opinion issued by Clare County Council on 22nd April 2024 accomanies this application. The de

Location
Co. Clare Map
Planning reference
2460411
Council planning fileGet alertsDownload PDF

Key facts

Received
29 Aug 2024
Refused
23 Oct 2024

Timeline

  1. Application received
  2. Refused

Outlook

What happens next

The application was refused on 23 Oct 2024. Work is not expected unless the decision is overturned on appeal or a new application is granted.

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2460411 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Clare County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near Co. Clare

Get alerts for Co. ClareFree. We email you when new applications appear.

Free email alerts

Get new Clare projects by email

New planning applications, decisions and site starts in Co. Clare. We only email when something new appears.

How often

We send a confirmation link first. No alerts until you click it.

Email alerts for this applicationMore alert options