Planning application · Co. Clare

Booltiagh, Ennis, Co. Clare

Granted 21 Aug 2026 (final grant issued 23 Sep 2026)

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560670 at Booltiagh, Ennis, Co. Clare: ~2 homes.
  • The applicant is Ørsted Onshore Ireland Midco Ltd. The agent is Fergus de Faoite.
  • It was received by Clare County Council on 31 Oct 2025.
  • Status: Granted 21 Aug 2026 (final grant issued 23 Sep 2026).
  • Permission was granted on 21 Aug 2026 and the final grant issued on 23 Sep 2026. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.

Source: the Clare County Council planning register, checked 17 Oct 2026. Open the council's file

More planning applications in Ennis · Planning applications in Co. Clare

What and where

~2 homes

for development at this site measuring c. 1.42 Ha located within the townland of Booltiagh, Ennis, Co. Clare. The development seeks to amend the Battery Energy Storage System (BESS) development permitted under ref. 23/60414 and the existing permanent 110kV Booltiagh Substation permitted under ref. 00/567 (ACP ref. 120616) amended by ref. 11/340, which are both co-located with the existing and operational Booltiagh wind farm. There are no proposed amendments to the permitted and operational wind farm. The amendments to the permitted BESS will consist of the excavation and removal of 0.36Ha of peat within the proposed fenced BESS enclosure area and the import of equivalent amount of stone to level the site; a revised BESS enclosure to occupy a reduced footprint and layout for the construction and operation of reduced battery array units (32 nos.) with built in inverters resulting in the exclusion of permitted standalone inverters; a revised control & SCADA room, inclusion of 2 no. auxiliary transformer units, 1 no. storage container, and 1 no. standby generator and fuel tank; replacement of permitted MVA transformers with 8 no. MVA Skids (transformers and switchgear); and a revised gated access point and roads; and the installation of a 230m long 20kV underground interconnector cable to connect the BESS control and SCADA room to the existing 110kV Booltiagh substation. The amendments to the permitted 110kV substation will consist of the replacement of the grid transformer in the IPP compound including 110kV circuit breaker, combined CT/VT, disconnector, earth switch and surge arrestors, two post insulators, two auxiliary transformers, one house transformer, one generator and diesel tank and underground cabling trenching; and revisions to permitted ancillary infrastructure layout including security fencing, lighting, lightening masts, two interface kiosks, and CCTV. This application seeks a 10-year duration of planning permission and 35-year duration of operational lifetime of the permitted BESS infrastructure. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Description as published by the council. Its text starts part-way through a sentence.

Location
Ennis, Co. Clare Map
Planning reference
2560670
Application type
Permission
Applicant
Ørsted Onshore Ireland Midco Ltd
Agent
Fergus de Faoite
Council planning fileGet alerts

Numbers and dates

Homes
~2estimated from the application
Estimated construction value
€290k to €440kOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Received
31 Oct 2025
Decision to grant
21 Aug 2026
Final grant
23 Sep 2026

Timeline

  1. Application received
  2. Further information requested
  3. Decision to grant
  4. Final grant issued

Site history

This site's history

  1. Earlier permission 2360414 for this site: granted 23 Nov 2023.

    for development which will consist of a 10 year planning permission for the construction and operation of battery arrays (240 number units… Named in this application's description

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Permission was granted on 21 Aug 2026 and the final grant issued on 23 Sep 2026. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2560670 on eplanning.ie: drawings, reports and the decision.Open the council's file

Reviewed build intelligence

What the documents establish

Government document review

Conditional decision notified 21 August 2026 following May further information and July clarification. A final grant, appeal outcome, commencement or commissioning is not established by the inspected files.

3 official documents inspected · Checked 2026-09-06 · Official file index

The August notification is a decision, not a final grant

Conditional decision; final grant not established · Clare reference 2560670; October 2025 application revised in May and July 2026

What the evidence says
Clare’s notice dated 21 August 2026 records a decision to grant subject to four conditions. It expressly states that work is not authorised until a final grant issues. The conditions provide for a ten-year permission period and a 35-year operational period measured from a commissioning date to be established in writing. They do not establish that commissioning has occurred.

Why it may matter — interpretation
Interpretation: separates a notified decision and its proposed operating period from final permission and actual operation.

What is not established
A final grant, appeal outcome, commencement and commissioning date have not been established.

Inspect the evidence

Booltiagh BESS amendment: conditional decision notice · p.4
NOT AUTHORISED · Issued 2026-08-21 · Four conditions; final grant expressly distinguished · Checked 2026-09-06

NOT AUTHORISED

Booltiagh BESS amendment: conditional decision notice · p.2
35 years · Issued 2026-08-21 · Four conditions; final grant expressly distinguished · Checked 2026-09-06

35 years

The BESS amendment has 32 arrays and eight skids

Conditional decision; final grant not established · BESS amendment to permission 23/60414; distinct from substation equipment and the operating wind farm

What the evidence says
The decision description retains 32 battery-array units with built-in inverters, replacing the previously permitted standalone inverter arrangement. The BESS scope also includes eight transformer/switchgear skids, a revised control/SCADA room, two auxiliary transformer units, one storage container and one standby generator with fuel tank. These are equipment quantities, not dwellings or confirmed purchases.

Why it may matter — interpretation
Interpretation: identifies the storage-side equipment package without summing repeated equipment terms across separate compounds.

What is not established
Selected manufacturers, contracted quantities, installed equipment and final MW/MWh capacity are not established.

Inspect the evidence

Booltiagh BESS amendment: conditional decision notice · p.1
battery array units (32 nos.) · Issued 2026-08-21 · Four conditions; final grant expressly distinguished · Checked 2026-09-06

battery array units (32 nos.)

A 230 m, 20 kV link connects to the 110 kV substation

Conditional decision; final grant not established · Grid-interface works under 2560670; substation history 00/567 and 11/340 is context

What the evidence says
The decision describes a 230 m underground 20 kV interconnector from the BESS control/SCADA room to the existing 110 kV substation. The substation amendment separately replaces the grid transformer and associated circuit breaker, CT/VT, disconnector, earth switch and surge arrestors, with ancillary transformers, generator, trenching and security infrastructure. The operational wind farm is explicitly outside the proposed amendments.

Why it may matter — interpretation
Interpretation: keeps the voltage levels and distinct storage/substation work packages connected without inventing an enlarged wind-farm project.

What is not established
Final equipment schedules, protection settings, grid energisation and construction contracts are not established.

Inspect the evidence

Booltiagh BESS amendment: conditional decision notice · p.1
230m long 20kV underground interconnector · Issued 2026-08-21 · Four conditions; final grant expressly distinguished · Checked 2026-09-06

230m long 20kV underground interconnector

The application report compares 240 earlier arrays with 32 larger units

Source wording clarified by the later decision; installation unverified · October 2025 design comparison and later August 2026 decision description

What the evidence says
The October addendum describes a change from 240 earlier battery arrays to 32 larger units, and from the previous transformer arrangement to eight skids. The August decision retains the 32-array/eight-skid description. This is a technology/layout revision, not 272 arrays and not a demonstrated change in total energy-storage capacity. An isolated sentence in the addendum says transformers are excluded, while its surrounding text and the later decision explicitly include transformer skids; that wording is not used to remove them from the package.

Why it may matter — interpretation
Interpretation: preserves the actual revision and an internal wording inconsistency without silently correcting the source.

What is not established
Comparable MW/MWh ratings and final procurement quantities remain unverified.

Inspect the evidence

Booltiagh Environmental Report Addendum · p.11
240no. units · Issued October 2025 (month only) · D02 drafted 16 October, reviewed/approved 28 October; received 31 October · Checked 2026-09-06

240no. units

Booltiagh BESS amendment: conditional decision notice · p.1
8 no. MVA Skids · Issued 2026-08-21 · Four conditions; final grant expressly distinguished · Checked 2026-09-06

8 no. MVA Skids

The later report resolves the earlier dewatering question

Later planning assessment; executed groundworks not established · August report after the July clarification; peat handling within the amended BESS enclosure

What the evidence says
The August planning report records a stated 4,600 m³ of peat to be removed. Its assessment accepts the applicant’s clarification that no on-site dewatering is proposed and notes the receiving licence holders’ written consent. Earlier questions about dewatering and disposal are therefore presented as a resolved review issue, not as an outstanding design requirement or proof that excavation has happened.

Why it may matter — interpretation
Interpretation: updates the groundworks position using the council’s later assessment.

What is not established
Actual excavation, transported quantities, waste acceptance records and site conditions have not been independently verified.

Inspect the evidence

Planning Application Report 3: July clarification assessment · p.6
4,600 m3 · Issued 2026-08-20 · Planner signed 19 August; senior endorsement dated 20 August · Checked 2026-09-06

4,600 m3

The temporary compound follows a separate exemption determination

Separate route recorded by the planner; no physical phase merge · Relationship described in the later planner assessment; the separate declaration document was not inspected

What the evidence says
The later planning report records that Clare issued a Section 5 declaration on 8 July 2026 for the temporary construction compound, reference R26/34. It also explains that the environmental screening considered the compound and the BESS amendment together. The compound’s planning route is separate; its inclusion in environmental assessment does not add another battery-storage phase.

Why it may matter — interpretation
Interpretation: distinguishes a separate consent route from the scope used for cumulative environmental assessment.

What is not established
The full Section 5 declaration and completed compound have not been independently inspected.

Inspect the evidence

Planning Application Report 3: July clarification assessment · p.6
temporary construction compound R26/34 · Issued 2026-08-20 · Planner signed 19 August; senior endorsement dated 20 August · Checked 2026-09-06

temporary construction compound R26/34
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 3 government-published PDFs were visually inspected. Seventy-seven public document rows were retained. Five PDFs had selected pages visually inspected; three support these published facts. Two drawing sheets were screened but their dimensional differences are not resolved or presented as final specifications. Proposals do not establish procurement or installed work.

How we know this

From the Clare County Council planning register, checked 17 Oct 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Ennis

Get alerts for EnnisFree. We email you when new applications appear.

Free email alerts

Get new Ennis projects by email

New applications, decisions and site starts in Ennis, Co. Clare. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options