Mixed use · Co. Cork
South Mall Court, 1-2 Beasley St, Co. Cork
Granted 17 Feb 2020 (final grant issued 30 Mar 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 1938970 at South Mall Court, 1-2 Beasley St, Co. Cork: ~3 homes.
- It was received by Cork City Council on 16 Dec 2019.
- Status: Granted 17 Feb 2020 (final grant issued 30 Mar 2020).
Source: the Cork City Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 17 Feb 2020.
Search the Cork City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
~3 homes
Permisssion sought for a) the change of use of 2 no vacant ground floor commercial units and for the provision of student accommodation in the form of 3 no apartments containing 11 no bed spaces along with kitchen and living rooms and all other ancillary spaces b) the demolition of an existing internal podium currently providing amenity space to the upper floor apartments, to provide a new amenity area at ground floor to serve the proposed and existing apartments c) internal alterations to facilitate the development of ground and first floor levels, d) elevational alterations to the front façade on Beasley St and on the internal courtyard e) elevations and all necessary and ancillary site works to complete the development
- Location
- South Mall Court, Co. Cork Map
- Council
- Cork City Council
- Planning reference
- 1938970
Numbers and dates
- Homes
- ~3estimated from the application
- Project type
- Mixed use
- Received
- 16 Dec 2019
- Decision to grant
- 17 Feb 2020
- Final grant
- 30 Mar 2020
- Site start notified
- 14 Jul 2020
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 1938970 on planning.corkcity.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Cork City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 14 Jul 2020Notice filed · Change of use of ground floor from retail to three number student apartmentsView the site start
- Completion certificate recordedRecorded in Jul 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.