Mixed use · Co. Cork
Ballydaheen Road/ Mill Street Ballydahin Mallow Co. Cork
Granted 25 Oct 2023 (final grant issued 1 Dec 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 22/6225 at Ballydaheen Road/ Mill Street Ballydahin Mallow Co. Cork: ~52 homes.
- It was received by Cork County Council on 4 Oct 2022.
- Status: Granted 25 Oct 2023 (final grant issued 1 Dec 2023).
- Work was due to start on 9 Oct 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 25 Oct 2023.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
~52 homes
The construction of 52 no. residential units comprising of 12 no. 3 bed units, 18 no. 2 bed units and 22 no. 1 bed units [a mix of 3 bed townhouses, 1 & 2 bed maisonettes and 1, 2 & 3 bed own-door apartments]. The units range in height from 2 to 3 storeys. Permission is also sought for the construction of 3 no. commercial units [Beauty Salon/Coffee Shop/Café and Newsagents] as well as a multi-purpose/ community space at ground floor level. The development also includes landscaping, drainage, boundary treatments, 96 no. bicycle parking spaces, 57 no. car parking spaces, bin storage, play area, planting/screening and all associated site development works at Ballydaheen Road/ Mill Street, Ballydahin, Mallow, Co. Cork. A Natura impact statement will be submitted to the planning authority with this application. The Natura impact statement will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the office of the relevant planning authority.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 22/6225
Numbers and dates
- Homes
- ~52estimated from the application
- Estimated construction value
- €7.6m to €15mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Mixed use
- Received
- 4 Oct 2022
- Decision to grant
- 25 Oct 2023
- Final grant
- 1 Dec 2023
- Site start notified
- 9 Oct 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 22/6225.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 9 Oct 2024Notice filed · The construction of 46 no. housing units, 3 commercial units and a multipurpose space...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.