Mixed use · Co. Cork

Ballydaheen Road/ Mill Street Ballydahin Mallow Co. Cork

Granted 25 Oct 2023 (final grant issued 1 Dec 2023)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 22/6225 at Ballydaheen Road/ Mill Street Ballydahin Mallow Co. Cork: ~52 homes.
  • It was received by Cork County Council on 4 Oct 2022.
  • Status: Granted 25 Oct 2023 (final grant issued 1 Dec 2023).
  • Work was due to start on 9 Oct 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 25 Oct 2023.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

~52 homes

The construction of 52 no. residential units comprising of 12 no. 3 bed units, 18 no. 2 bed units and 22 no. 1 bed units [a mix of 3 bed townhouses, 1 & 2 bed maisonettes and 1, 2 & 3 bed own-door apartments]. The units range in height from 2 to 3 storeys. Permission is also sought for the construction of 3 no. commercial units [Beauty Salon/Coffee Shop/Café and Newsagents] as well as a multi-purpose/ community space at ground floor level. The development also includes landscaping, drainage, boundary treatments, 96 no. bicycle parking spaces, 57 no. car parking spaces, bin storage, play area, planting/screening and all associated site development works at Ballydaheen Road/ Mill Street, Ballydahin, Mallow, Co. Cork. A Natura impact statement will be submitted to the planning authority with this application. The Natura impact statement will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the office of the relevant planning authority.

Location
Co. Cork Map
Planning reference
22/6225

Numbers and dates

Homes
~52estimated from the application
Estimated construction value
€7.6m to €15mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Mixed use
Received
4 Oct 2022
Decision to grant
25 Oct 2023
Final grant
1 Dec 2023
Site start notified
9 Oct 2024

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 9 Oct 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 22/6225.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 9 Oct 2024Notice filed · The construction of 46 no. housing units, 3 commercial units and a multipurpose space...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options