Commercial fit-out, Cork, Cork - Planning Application 2341944
Cork / Cork / Cork, Cork
Source-linked planning record
Commercial fit-out, Cork, Cork - Planning Application 2341944
Cork / Cork / Cork, Cork- PB ref
- PB-27809
- Plan ref
- 2341944
- Authority
- Cork City Council
- Stage / date
- Commencement / 16 Sep 2024
- Est. value band
- Value not disclosed
- Project class
- Commercial fit-out
- Promoter
- not available yet
- Architect / agent
- Cumnor Construction
Source: http://planning.corkcity.ie/AppFileRefDetails/2341944/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Cork City Council
- Application reference
- 2341944
- Applicant
- not available yet
- Agent
- Cumnor Construction
- Decision stage
- Commencement
- Commenced
- 16 Sep 2024
- Builder / developer
- Cumnor Construction
Official description
Verbatim source text
Permission for the construction of an indoor training facility development which will contain a synthetic all-weather playing surface, gymnasium, changing rooms, treatment rooms, storage, office/administration space, staff welfare areas and new signage. Permission is also sought for a new pedestrian access from Pearse Road, and shared car parking area on Pearse Road, new parking area within the site and all other ancillary site works including a ticketing booth and bicycle parking. The proposed development is a change of plan from that previously permitted by Cork City Council planning reference 18/38083.
Verify against official sourceMore Cork planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- not available yet
- Planning agent
- Cumnor Construction
- Builder / developer
- Cumnor Construction
Lifecycle timeline
Application to site progress
-
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Completed
Completion certificate recorded CC00000057919CY · commencement CN0119169CY · recorded in Sep 2024 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 2 Aug 2026.
Likely trades & supplier leads