Infrastructure · Co. Cork

Gallanes Clonakilty Co. Cork

Granted 9 Sep 2024

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 24/240 at Gallanes Clonakilty Co. Cork: Retention of external hardstanding area for trailer parking ancillary…
  • It was received by Cork County Council on 14 May 2024.
  • Status: Granted 9 Sep 2024.
  • Work started on site on 8 Apr 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 9 Sep 2024.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Retention of external hardstanding area for trailer parking ancillary…

Permission for Retention of external hardstanding area for trailer parking ancillary to existing factory. Permission for the following: a) Change of use of part of existing Offices/Staff Facilities to Production Area and raise roof level over existing and new Production Area on western side of existing factory b) Construct a new Production Area extension to the western side of existing factory, c) Construct a new Dispatch Area extension and raise roof level over part of existing Dispatch Area to the southern side of existing factory, d) Construct a new Dry Goods Store extension to the eastern side of existing factory, e) Construct a new extension to the existing Offices at ground floor level and construct a new first floor extension over the existing Offices on the western and southern sides, f) Construct a new pedestrian bridge over Dispatch yard on southern side of existing factory, g) Fenestration changes to elevations, h) Construct a new access road and carpark to the western side of existing factory along with all associated site works

Location
Co. Cork Map
Planning reference
24/240
Application type
Retention permissionPermission to keep work already carried out.

Numbers and dates

Project type
Infrastructure
Received
14 May 2024
Granted
9 Sep 2024
Site start
8 Apr 2025

Timeline

  1. Application received
  2. Granted
  3. Site start

Outlook

What happens next

Work started on site on 8 Apr 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 24/240.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 8 Apr 2025Work started · Material alteration to include construction of new, 2 story portal frame factory...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options