Large residential · Co. Cork
Cois Máigh Mogeely Co.Cork
Granted 9 Dec 2024 (final grant issued 22 Jan 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 24/4658 at Cois Máigh Mogeely Co.Cork: ~20 homes.
- It was received by Cork County Council on 18 Apr 2024.
- Status: Granted 9 Dec 2024 (final grant issued 22 Jan 2025).
- Work was due to start on 11 Feb 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 5 Oct 2026. Search the council's register
Council register
The council's register shows: Granted on 9 Dec 2024.
Search the Cork planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
~20 homes
Permission for residential development consisting of the construction of 20 no. dwelling units and all associated ancillary development works including parking, drainage, landscaping and amenity areas. Access to the Mogeely road will be via the existing estate roads
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 24/4658
Numbers and dates
- Homes
- ~20estimated from the application
- Estimated construction value
- €2.9m to €4.4mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 18 Apr 2024
- Decision to grant
- 9 Dec 2024
- Final grant
- 22 Jan 2025
- Site start notified
- 11 Feb 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 24/4658.Search the register
How we know this
From the Cork County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 11 Feb 2025Notice filed · phase 1 · Construction of 10no. two storey dwellings at Cois Maigh, Mogeely, Co. Cork. [House Nos...View the site start
- 12 May 2025Notice filed · phase 2 · Construction of 2no. three storey dwellings at Cois Maigh, Mogeely, Co. Cork. [House Nos...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.