Infrastructure · Co. Cork

Dereenacreenig West Wind Farm Ltd., Dreenacreenig West, Drimoleague, Co. Cork

Under appeal since 27 Apr 2026 (Granted 14 Apr 2026 by the council)

Get updates on this application

We'll email you if the decision is appealed and when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 25/6052 at Dereenacreenig West Wind Farm Ltd., Dreenacreenig West, Drimoleague, Co. Cork: Windfarm development.
  • It was received by Cork County Council on 29 Sep 2025.
  • Status: Under appeal since 27 Apr 2026 (Granted 14 Apr 2026 by the council).
  • The council's decision was appealed to An Coimisiún Pleanála. The appeal decides the outcome, and building work cannot start before it.

Source: the Cork County Council planning register, checked 2 Jun 2026. Open the council's file

More planning applications in Drimoleague · Planning applications in Co. Cork

What and where

Windfarm development

Permission for a windfarm development at this site within the townland of Derrenacrinnig West. The proposed Grid Connection traverses the townlands of Derreenacrinnig West, Barnagowlane West, Glanareagh, Gortnacowly, Ards Beg, Ardrah, Laharanshermeen, Maulraha, Maulikeeve, Derryarkane, Cappanaboul, Skahanagh, Gortroe, Shandrum Beg, Shandrum More, Dromloughlin, Ballylickey, Crossoge. Temporary works will be required to accommodate the delivery of the turbine components. These temporary works are included as part of this application and are located in the townlands of Castledonovan, Derreenacrinnig East, and Derreenacrinnig West. The development will consist of: Construction of 3 no. wind turbines with an overall ground to blade tip height of 119.3m with a rotor diameter of 82m and a hub height of 78.3m. Construction of 1 no. permanent 20 kV Electrical Substation, all associated electrical plant and equipment, all associated underground cabling, and all ancillary structures and works. Construction of one Temporary Construction Compound with associated temporary site offices, parking areas and security fencing. Upgrade and reuse of existing hardstands. Upgrade and reuse of existing internal site access roads. Provision of Biodiversity Enhancement Area. All associated underground electrical and communications cabling connecting the wind turbines to the wind farm Electrical Substation. Construction of approximately 10.75 km of 20kV overhead line (OHL) Grid Connection, the OHL to be constructed consists of c. 157 wood poles (ranging from 9m to 15m above ground) supporting electrical conductor lines and ancillary structures and equipment. Installation of approximately 3.3km of underground cable ducting Grid Connection and associated electrical cabling, and all other ancillary works including joint bays, culverts, marker posts and all associated developments. Construction Haul Route works along the L-8767, L-4711 and L-8765. A 10 year permission and a 40 year operational period from the date of overall commissioning of the entire wind farm is being sought. However, part of the substation and all of the Grid Connection will be owned and operated by ESB networks and as part of the national grid infrastructure, their life can extend beyond the life of the windfarm. Accordingly, permission is sought for the Grid Connection and substation in perpetuity. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413). This planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. apply. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) has been prepared and will be submitted with the application. The planning application and EIAR may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy at the offices of the Planning Authority, Norton House, Cork Road, Skibbereen, Co. Cork. P81AT28 during its public opening hours, I.e. 9.00am to 4.00 p.m. Monday to Friday (excluding public holidays). A submission or observation in relation to the application and EIAR may be made in writing to the Planning Authority on payment of the prescribed fee, €20, within the period of 5 weeks, beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.

Location
Drimoleague, Co. Cork Map
Planning reference
25/6052

Numbers and dates

Project type
Infrastructure
Received
29 Sep 2025
Council decision
14 Apr 2026
Appeal lodged
27 Apr 2026

Timeline

  1. Application received
  2. Granted by the council
  3. Appeal lodged

Outlook

What happens next

The council's decision was appealed to An Coimisiún Pleanála. The appeal decides the outcome, and building work cannot start before it.

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Cork County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near Drimoleague

Get alerts for DrimoleagueFree. We email you when new applications appear.

Free email alerts

Get new Drimoleague projects by email

New applications, decisions and site starts in Drimoleague, Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options