Section 5 declaration · Co. Dublin

The Iveagh Hostel, Bride Road, Dublin 8

Decision to grant in part, refuse in part 22 Oct 2026

Key facts

  • Section 5 reference 0411/26 at The Iveagh Hostel, Bride Road, Dublin 8: EXPP: PROTECTED STRUCTURE: Whether the following works at the Iveagh Hostel, Bride Road, Dublin 8 (a protected structure) are or are not exempted development, comprising internal refurbishment of an existing ground-floor bedroom wing (Bedrooms 78-88, Lounge 02, Kitchen 03, Shower Rooms 05/06, Toilets 07/08, Store 04 and Corridor 01) and associated works outlined as follows: (a) Internal fabric strip-out: (i) removal of non-original wall linings and services boxing from internal face of external walls and from one side of existing stud partitions; (ii) removal of existing suspended ceiling grid and tiles; (iii) removal of existing non-original vinyl floor tiling; (b) Internal fabric fit-out: (i) reinstatement of new independent stud lining and plasterboard to walls with sound insulation, fire-stopping and services renewal, minor adjustment of door openings in non-original partitions, and re-tiling of shower rooms/WCs with replacement sanitaryware and vanity units; (ii) installation of new independently-supported suspended ceiling grid and tiles; (iii) replacement of floor finishes throughout; (iv) replacement of internal doors, frames, skirtings and architraves with new fire-rated doorsets and joinery; (v) replacement of kitchenette units and appliances; (vi) redecoration of existing windows, with no alteration to fabric; (c) Mechanical and electrical works: (i) strip-out of existing services and fire/life-safety installations; (ii) renewal of electrical services, emergency lighting, signage and fire alarm installation; (iii) replacement of existing MVHR ductwork, extended to serve 16 no. bedrooms; (iv) replacement of existing heating pipework to existing boiler; (v) renewal of existing MCC panel (basement) and fire alarm panel (main office); replacement of non-original external vent covers with powder-coated covers colour-matched to existing rainwater goods; relining of existing boiler flues with twin-wall flue liner.
  • The applicant is the Iveagh Trust. The agent is Deirdre Keeley Care of Dathanna Architecture.
  • It was received by Dublin City Council on 25 Sep 2026.
  • Status: Decision to grant in part, refuse in part 22 Oct 2026.
  • The council's declaration: Split decision - expp, 22 Oct 2026.

Source: the Dublin City Council planning register, checked 5 Nov 2026. Open the council's file

More planning applications in Dublin 8 · Planning applications in Co. Dublin

What and where

Section 5 declaration request: EXPP: PROTECTED STRUCTURE: Whether…

EXPP: PROTECTED STRUCTURE: Whether the following works at the Iveagh Hostel, Bride Road, Dublin 8 (a protected structure) are or are not exempted development, comprising internal refurbishment of an existing ground-floor bedroom wing (Bedrooms 78-88, Lounge 02, Kitchen 03, Shower Rooms 05/06, Toilets 07/08, Store 04 and Corridor 01) and associated works outlined as follows: (a) Internal fabric strip-out: (i) removal of non-original wall linings and services boxing from internal face of external walls and from one side of existing stud partitions; (ii) removal of existing suspended ceiling grid and tiles; (iii) removal of existing non-original vinyl floor tiling; (b) Internal fabric fit-out: (i) reinstatement of new independent stud lining and plasterboard to walls with sound insulation, fire-stopping and services renewal, minor adjustment of door openings in non-original partitions, and re-tiling of shower rooms/WCs with replacement sanitaryware and vanity units; (ii) installation of new independently-supported suspended ceiling grid and tiles; (iii) replacement of floor finishes throughout; (iv) replacement of internal doors, frames, skirtings and architraves with new fire-rated doorsets and joinery; (v) replacement of kitchenette units and appliances; (vi) redecoration of existing windows, with no alteration to fabric; (c) Mechanical and electrical works: (i) strip-out of existing services and fire/life-safety installations; (ii) renewal of electrical services, emergency lighting, signage and fire alarm installation; (iii) replacement of existing MVHR ductwork, extended to serve 16 no. bedrooms; (iv) replacement of existing heating pipework to existing boiler; (v) renewal of existing MCC panel (basement) and fire alarm panel (main office); replacement of non-original external vent covers with powder-coated covers colour-matched to existing rainwater goods; relining of existing boiler flues with twin-wall flue liner.

Location
Dublin 8, Co. Dublin Map
Planning reference
0411/26
Agent
Deirdre Keeley Care of Dathanna Architecture

Numbers and dates

Received
25 Sep 2026
Decision to grant in part, refuse in part
22 Oct 2026
Protected structure
Yes

Timeline

  1. Application received
  2. Decision to grant in part, refuse in part

Outlook

What happens next

The council's declaration: Split decision - expp, 22 Oct 2026.

Work packages named so far

  • Conservation work to a protected structureNamed in the application description
  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 0411/26 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Dublin City Council planning register, checked 5 Nov 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near Dublin 8

Get alerts for Dublin 8Free. We email you when new applications appear.

Free email alerts

Get new Dublin 8 projects by email

New applications, decisions and site starts in Dublin 8, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options