Protected structure · Co. Dublin
The Fleet Street Hotel, Fleet Street, Dublin 2
Granted 11 Oct 2019 (final grant issued 19 Nov 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 2 by email
Key facts
- Planning application 3100/19 at The Fleet Street Hotel, Fleet Street, Dublin 2: Change of use of existing ancillary accommodation to 7 no. additional…
- It was received by Dublin City Council on 27 May 2019.
- Status: Granted 11 Oct 2019 (final grant issued 19 Nov 2019).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 2 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 11 Oct 2019.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Change of use of existing ancillary accommodation to 7 no. additional…
PROTECTED STRUCTURE: Permission for the change of use of existing ancillary accommodation to 7 no. additional bedrooms all at First Floor level, resulting in an overall increase in the total number of bedrooms in the existing hotel from 93 to 100. This application will not affect the existing permission for 11 additional bedrooms (Reg. Ref. 2149/17). The proposed works comprise of internal alterations to the existing layouts with minor elevational modifications to non-original windows facing internal roofed areas. The proposed development consists of development to a Protected Structure in accordance with the Dublin City Council Record of Protected Structures (RPS Reference Nos. 2920 and 8537). The development is located within a Conservation Area and an Architectural Conservation Area.
- Location
- Dublin 2, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3100/19
Numbers and dates
- Project type
- Protected structure
- Received
- 27 May 2019
- Decision to grant
- 11 Oct 2019
- Final grant
- 19 Nov 2019
- Site start notified
- 18 Mar 2020
- Protected structure
- Yes
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3100/19.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 18 Mar 2020Notice filed · phase 1 · Material Alterations to the First FloorView the site start
- 9 Jan 2023Notice filed · phase 2 · Material Alteration to the first floor at the existing Fleet Street Hotel, Fleet Street...View the site start
- Completion certificate recordedRecorded in Jan 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area